Electrical installation 73
Connection procedure – cable glands at the cable lead-through
For description of the cable glands, see chapter
Operation principle and hardware
, page
WARNING!
Read and follow the instructions given in chapter
. Ignoring
the instructions can cause physical injury or death, or damage to the equipment.
1. Open the door of the incoming cubicle. Unlock the handle, release it from the holder
and turn upwards to release the door locking mechanism.
2. Remove the shroud that protects the grid cable connection busbars and cable entries.
3. When shielded cable is used:
Lead the cables into the inside of the cubicle through the IP sealing glands. Ground a
shielded cable 360° at cabinet PE busbar lead-through with an EMC cable gland (to
be supplied by the customer).
Connect the cables as follows:
•
Twist the cable shields into bundles and connect to cabinet PE (ground) busbar.
Connect any separate ground conductors or cables to cabinet PE (ground)
busbar.
•
Connect the phase conductors to terminals L1, L2 and L3. Tighten the phase
conductors and PE to 70 N·m (50 lbf·ft) torque.
When single-core cables without metal shield are used:
•
Lead the cables into the inside of the cubicle through the IP sealing glands.
•
Connect the phase conductors to terminals L1, L2 and L3, and the PE conductors
to the PE terminal. Tighten the phase and PE conductors to 70 N·m (50 lbf·ft)
torque.
4. Provide support for the cables whenever necessary.
5. Refit all shrouds removed earlier and close the door.
Содержание ACS800-67LC
Страница 1: ... ABB WIND TURBINE CONVERTERS ACS800 67LC wind turbine converters Hardware manual ...
Страница 4: ......
Страница 16: ...16 Safety instructions ...
Страница 22: ...22 Introduction to the manual ...
Страница 42: ...42 Operation principle and hardware description ...
Страница 52: ...52 Mechanical installation ...
Страница 79: ...Electrical installation 79 3 3 Rotor side cable connection terminals U2 V2 W2 ...
Страница 92: ...92 Maintenance 4 6 5 5 ...
Страница 103: ...Maintenance 103 Bussmann fuses Mersen fuses ...
Страница 109: ...Maintenance 109 5 6 7 ...
Страница 131: ...Technical data 131 Declaration of incorporation ...
Страница 136: ...136 Dimension drawings ACS800 67LC 1075 0575 7 and 1375 0575 7 ...
Страница 137: ...Dimension drawings 137 With 400 mm wide incoming cubicle option C111 ...
Страница 138: ...138 Dimension drawings ACS800 67LC 1375 1125 7 ...
Страница 139: ...Dimension drawings 139 With 400 mm wide incoming cubicle option C111 ...
Страница 140: ...140 Dimension drawings ACS800 67LC 1595 0865 7 and 2035 1125 7 ...
Страница 141: ...Dimension drawings 141 With 400 mm wide incoming cubicle option C111 ...
Страница 143: ...Dimension drawings 143 Options 2H370 and C111 Option 1H371 ...
Страница 144: ...144 Dimension drawings Options 1H371 and C111 Options 2H371 and C111 ...
Страница 145: ...Dimension drawings 145 Option H378 Options H378 and C111 ...
Страница 147: ...Dimension drawings 147 Option 2H372 ...
Страница 148: ...148 Dimension drawings Option 3H372 ...
Страница 149: ...Dimension drawings 149 Option 1H373 ...
Страница 150: ...150 Dimension drawings Option 2H373 ...
Страница 151: ...Dimension drawings 151 Option 3H373 ...
Страница 152: ...152 Dimension drawings Option H375 ...