1 – First start assistant guided settings:
Language, date and time, and motor nominal values
Have the motor or pump name plate data at hand.
Power up the drive.
The First start assistant guides you through the first start-up.
The assistant begins automatically. Wait until the control panel
enters the view shown on the right.
Select the language you want to use by highlighting it (if not already
highlighted) and pressing
(
OK
).
Set the date and time as well as date and time display formats.
• Go to the edit view of a selected row by pressing .
• Scroll the view with and .
Go to the next view by pressing
(
Next
).
To change a value in an edit view:
• Use and to move the cursor left and right.
• Use
and to change the value.
• Press
(
Save
) to accept the new setting, or press
(
Cancel
) to go back to the previous view without making
changes.
To give the drive a name that will be shown at the top, press . If
you do not want to change the default name (IRR), continue by
pressing
(
Next
).
Hint: Name the drive, for example, Pump 1.
ACQ580 ULH Irrigation drives: Select the supply voltage with
parameter 95.01 Supply voltage:
• In the First start assistant menu, select Exit and press
(
Next
).
• In the Home view, press
(
Menu
) to enter the Main menu.
• In the Main menu, go to
Parameters >
Complete list > 95 HW
configuration
by selecting the correct row and pressing
(
Select
) repeatedly.
• Select parameter 95.01 Supply voltage and press
(
Edit
).
• Select supply voltage
380…415
or
440…480
using keys
and
. Press
(
Save
).
• Go back to the Main menu by pressing
(
Back
) repeatedly.
• In the Main menu, select
First start assistant
and press
(
Select
) to enter the First start assistant menu.
Continue with the following steps for commissioning the ACQ580.