Installation Preparation
3
Installation Preparation
The site is prepared mostly during the site planning stage, as described in the
environmental spec for MX-ONE SITE PLANNING. Should these preparations
not be complete, perform the following steps before starting the installation:
1.
Mark where to position the equipment and where to mount wall supports
(if required).
2.
Drill holes for anchoring the rack to the floor (use the rack and the tip
protection as a template).
3.
If necessary, make holes for the running of cables between rooms.
4.
If required, set up cable chutes in the site.
5.
Clean the room before unpacking the equipment.
3.1
Tools
The following tools are required for hardware installation in a BYB 501 cabinet:
Table 5
Tools
Tool
Product Number
Dimensions
Used for
Set of tools
LTT 999 08/1
U-Ring wrench
LSB 116 24
W = 24 mm
Tip protection and
cabinet feet
U-Ring wrench
LSB 116 13
W = 13 mm
Battery pole nuts
Torx T30 screwdriver
LSA 126 11/30
Door set
Torx T20 screwdriver
LSA 126 11/20
ESD-cover, air
plates
Torx T8 screwdriver
LSA 126 11/8
Air plates, board
fronts, and cable
connectors
Hexagon key set
LSB 904 21
45 x 14 x 1.5
mm
Door set
Slotted screwdriver 3x0.5
LSA 1001/2
161 x 3 x 0.5
mm
For connection of
AC/DC unit
PH2 screwdriver (Philips2)
LSA 122 12/2
L = 200 mm
For earthing of
AC/DC unit
21
6/1531-ASP 113 01 Uen J2 2008-07-17
Содержание MX-ONE
Страница 1: ...Installing MX ONE INSTALLATION INSTRUCTIONS...
Страница 6: ...Installing MX ONE 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 10: ...Installing MX ONE Figure 1 MX ONE Cabinets 4 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 26: ...Installing MX ONE 20 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 72: ...Installing MX ONE Figure 49 Installing Slides 66 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 97: ...Cabling Figure 71 Connecting the Batteries in a 115 230 V System 91 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 102: ...Installing MX ONE Figure 76 AC DC Cabling to the Subracks in 115 230V Systems 96 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 107: ...Cabling Figure 79 Cable Connections Configure Example 101 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 110: ...Installing MX ONE Figure 80 TLU77 TMU TLU76 ELU33 ELU34 and IPLU Board Fronts 104 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 111: ...Cabling Figure 81 ESU Front Connectors and LEDs 105 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 112: ...Installing MX ONE Figure 82 DC DC Front Connectors and LEDs 106 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 114: ...Installing MX ONE Figure 85 TLU77 Front Connectors and LEDs 108 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 122: ...Installing MX ONE 116 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 134: ...Installing MX ONE 128 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 146: ...Installing MX ONE 140 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 148: ...Installing MX ONE 142 6 1531 ASP 113 01 Uen J2 2008 07 17...
Страница 156: ...Installing MX ONE 150 6 1531 ASP 113 01 Uen J2 2008 07 17...