Figure 2
Electrical
1.
Test the GFCI breaker protecting the spa for proper operation.
2.
Disconnect power to the spa.
3.
Connect the Aquatic 2 cord to the mating connector(s) on the spa control box as
described in the spa’s installation manual and Figure 2.
4.
Where possible, route the power cord away from other electrical lines. Do NOT run
the power cord parallel to any low voltage signal wires.
5.
Secure the power cord as required to prevent damage.
1.
With the spa filled to the proper level, run the spa controller through several cycles.
2.
Verify that the Aquatic 2 turns on and off as required by the controller.
3.
The red LED light will be visible from the viewing window on the bottom left.
4.
Verify that gas is flowing into the injector (there should be no water in the tubing and
very small bubbles entering the spa through the return).
5.
Verify that water does not push past the check valve during any spa cycle.
6.
Check for and correct any leaks.