A.R.I. Eliptix R-30 SRM 3W Скачать руководство пользователя страница 5

R-30 SRM 

 

 

 

 

 

 

 

Installation 

1.

 

Install the product according to the detailed Installation Instructions provided with it by A.R.I. and according to the 

description given in this manual. 

2.

 

The user should install manual Isolation Valves at the valve's upstream and downstream ports. 

3.

 

In all installation sites, the user should enable good visibility and verify that the work and auxiliary equipment used 

are done in accordance with the relevant local authorized standards. Extra safety considerations should be taken 
on hazardous environment sites. 

4.

 

Check and re-tighten the bolts connecting the product to the pipeline during commissioning and before operating 

the product for the first time. 

 

Commissioning and Operation 

1.

 

Read carefully the operation instructions prior to any attempt to operate the product. 

2.

 

Observe  the  safety  stickers  on  the  product  (when  exist)  and  never  perform  any  operation  contradicting  the 

instructions given. 

3.

 

In  order  to  achieve  maximum  performance  and  smooth  operation  of  the  product,  it  is  crucial  to  perform  the 

startup and first operation procedures exactly as described in this manual. 

4.

 

In cases where formal commissioning procedure is required, it should be done by an authorized A.R.I. technician 

prior to the first operation of the product. 

 

Maintenance 

Before any maintenance or non-regular operation, please read the following: 

1.

 

Servicing the product should be done only by qualified technicians for this type of work. 

2.

 

Make  sure  that  you  know  the  exact  type  of  the  system  fluid.  Act  accordingly  and  comply  with  all  the  relevant 

standards and regulations set for handling this type of fluid. 

3.

 

Before disconnecting the product from the system and before releasing the residual pressure do NOT: 

-

 

loosen or unscrew the product bolts; 

-

 

remove any protection cover; 

-

 

Open any service port. 

4.

 

Before any maintenance or non-regular operation, shut off the Isolation valves and release the residual pressure: 

A.

 

 For control valves with a pressure release outlet, slowly open the pressure release plug or the ball valve and make 

sure that all pressure is released.  

B.

 

 For  control  valves  without  a  pressure  release  outlet,  slowly  unscrew  the  flange  bolts  until  all  the  pressure  is 

released from the valve. 

5.

 

Make sure the control valve is empty of all liquid prior to commencing maintenance. 

6.

 

Remove the product from the line only after ensuring that internal pressure has been released. 

7.

 

Place warning signs around the work area as required by the local standards and procedures. 

8.

 

Inspect the product’s safety stickers and replace any damaged or faded sticker. 

9.

 

Manual cleaning of the product and/or its components using high water pressure or steam should be performed in 

accordance with its specific cleaning instructions, the local standards and regulations and without endangering the 
operator or the vicinity. 

10.

 

Manual  cleaning  of  product  and/or  its  components  using  acid  or  other  chemical  agents  should  be  performed  in 

accordance with the specific cleaning instructions, the relevant safety instructions for using that chemical as given 
by its supplier, the local standards and regulations and without endangering the operator or his vicinity. 

11.

 

For products used in potable water systems, if it is required to disinfect the product, do so according to the local 

water authority standards and regulations before putting the product into service. 

Содержание Eliptix R-30 SRM 3W

Страница 1: ...cape and infrastructure applications The R 30 series has an innovative elliptic shaped diaphragm that integrates well with a wide variety of regulating control pilots solenoids and control accessories...

Страница 2: ...n 6 2 INSTALLATION 7 2 1 Pre installation requisites 7 2 2 Installation procedure 8 2 3 Initial Start up The Control Valve 9 2 4 Initial Set up The Pressure Reducing and Sustaining Application 10 3 OP...

Страница 3: ...oever whether caused by accessing and or relying upon this Disclaimer and or in any document enclosed hereto including without limitation any links procedures or materials A R I shall NOT assume any l...

Страница 4: ...prior warning Make sure that allproducts outlet portsarenotdirectedtowardelectricalelements pumps orpeople 8 Always open and close valves slowly and gradually 9 Please note that the maximum working pr...

Страница 5: ...ulations set for handling this type of fluid 3 Before disconnecting the product from the system and before releasing the residual pressure do NOT loosen or unscrew the product bolts removeanyprotectio...

Страница 6: ...ons 2 Make sure that all the tools ladders lifting devices etc used during the maintenance procedures are taken away from the product area and stored 3 Remove grease and fat material residues in order...

Страница 7: ...Before installing the valve flush the pipeline to remove scale dirt and other particles that might affect the valve performance 3 Carefully remove the valve from the shipping package Unload all the va...

Страница 8: ...f the control valve 12 12a Air valves upstream and downstream of the control valve 15 Quick pressure relive valve downstream of the control valve 16 3 Turn the 3 way manual selector ball valve 3 to Cl...

Страница 9: ...2a slowly clockwise one turn at a time Wait few seconds between turns allowing the valve to react until the downstream pressure reaches the required level water starts to flow to the pipeline 7 Gradu...

Страница 10: ...ontrol chamber by letting water enter the control chamber through its port 4 causing the valve s diaphragm to slightly close and decrease the downstream pressure back to the required settings level Wh...

Страница 11: ...e set level When the upstream pressure drops below the setting the valve closes Pipeline water flows constantly through the control loop The pilot senses the upstream pressure through its 1 port When...

Страница 12: ...ease note By doing so you will have no control over the downstream pressure it is possible that your system will be exposed to excessive pressure 2 To manually close the valve turn the manual 3 way se...

Страница 13: ...ally inspect the valve s diaphragm for any tears 2 Every 12 months inspect the valve s operation and clean the Finger Filter 3 Check the downstream pressure adjust if required 4 2 Storing the valve It...

Страница 14: ...off the water supply to the valve Remove the bonnet and diaphragm remove the foreign object and check that the diaphragm body and cover are not damaged 2 The diaphragm is damaged 2 The valve is consta...

Страница 15: ...R 30 SRM 6 DIMENSIONAL DRAWING...

Страница 16: ...ble nor does this warranty extended to any consequential or incidental damages or expenses of any kind or nature regardless of the nature thereof including without limitation injury to persons or prop...