3-18
Installation Flow for an IRF
Figure 3-24
Installation flow for an IRF
Table 3-4
Description of the installation flow for an IRF of switches
No
Task
Remarks
1
Draw a plan for
an IRF with
switches
Take the following into consideration:
z
Number of IRF members and the bandwidth
z
Interface modules and cables
z
Physical connection mode( daisy chain connection or ring connection)
z
Cable connection
For details, see
Drawing a Plan for an IRF with Switches
2
Install the IRF
members to the
correct position
For detailed installation procedures, see:
z
Installing the Switch into a 19-Inch Rack Using Mounting Brackets
z
Mounting the Switch on a Workbench
.
3
Connect
grounding
cables and
power cords for
the switches
For details, see:
z
Connecting the Grounding Cable
z