Multi-GEM 12 is installed in electric distribution and local panels for supplying power 
to their production line. It measure the voltage and current, and calculate the power in 
real-time. You can monitor and manage the energy of equipment. It can help to 
operate efficiently and to reduce the energy consumption. 

This equipment is capable of accurate analysis and diagnosis equipment for various 
problems of energy management and power plants.

 Multi channel power meter (Multi-GEM 12) is able to measure and monitor multi 

    electric power loads.

 Max 12 single phase or 4 3P4W feeders power monitoring 

 Measurement : V (L-N, L-L) , A, Hz, PF, Unbalance, Power(P,Q,S), Energy (P,Q,S). 

 1.0/0.5 Class accuracy for power measurement conformed by IEC61557-12

 Flexible application for the single phase/ 3phase 4wire / 3phase 3wire power line.

 Sag/Swell / Over Current / Temp Alarm.

 Total Harmonics Distortion (THD)

 Support Ethernet (Modbus TCP) and Wi-Fi. 

 Support Cloud energy platform.

 Compact size for easy installation in narrow space (62 x 96 x 56 mm)

Measurement

1. Introduction

2. Characteristics

3. Specification

Model

Power system

Power Input

Communication

Usage

Altitude up to

Operating Temperature

Storage Temp.

Humidity

Standards

Voltage

Frequency

CT type

Measuring

Inputs 

Rating

Specification

3P3W, 3P4W, 1P2W, 1P3W
100~240 VAC, Max. 50/60 Hz

415 V 3~ L-L (240V L-N), CAT Ⅲ Max. 1000 A, 3~

50/60 Hz
100mA or 333mV
LAN 
Wi-Fi (Option)
Indoor
2,000 m 

-10℃~55℃
-25℃~70℃

Maximum relative humidity 80% R.H. for tempera-
tures up to 31 °C decreasing linearly to 50 % R.H. 
relative humidity at 40 °C
IEC 61557-12

   

 

Phase voltage

Line voltage
Line current

Active power

Reactive power

Apparent power

Frequency

Unit

V
V
A

W

Var

VA
Hz

Digit

0.0 ~ 99,999
0.0 ~ 99,999
0.0 ~ 99,999

±0 ~ 999,999,999
±0 ~ 999,999,999

0.0 ~ 999,999,999

45.00 ~ 65.00

±0.2% Reading
±0.2% Reading
±0.2% Reading

Class 0.5S
Class 0.5S
Class 0.5S

Item

Accuracy

Display

Power Factor

Temp. (NTC)

Voltage unbalance
Current unbalance

Phase angle

THD

Active Energy

Reactive Energy

Apparent Energy

Unit

%

%
%

°

%

kWh

kVarh

kVAh

± 100.00

-20.0 ~ 100.00

00 ~ 100.00
00 ~ 100.00
00 ~ 360.00
00 ~ 100.00

0.0 ~ 999,999,999
0.0 ~ 999,999,999
0.0 ~ 999,999,999

±0.5% Full scale

Item

Accuracy

Display

It needs to avoid a place where direct interference exists like as high temperature and 
electromagnetic field for the installation. Please check the environment condition 
around Multi-GEM 12 below for a correct operation.

1. Create two 4mm holes using the mounting hole guide in manual.

    → The upper left and lower right position of the 68 x 46mm rectangle. 

2. Fix the product by using bolts provided.

5. Name of parts

4. Installation

No.

1
2

3

4

5

6

7
8

Name

Screw fixing holes

Control Power

Voltage Input

Ethernet Port

CT Port

Status LED

Wall mount

Upgrade Port

Description

Screw holes for fixed terminals 
Supply  the control power to the gems 3512 (AC/DC 100~240V)
, Wire Size : 12 ~ 24AWG
N : Neutral (AC), -(DC) connection, A : Line (AC), +(DC) connection
Voltage input terminal  for measurement , Wire Size : 12 ~ 24AWG
Communication with Master (Modbus Slave) 
Protocol : Modbus TCP/IP
Speed : 10/100 Mbps Automatic selection
CT Input Terminal
Cloud Version 

Bolt spec : D = 4mm / L = 55mm 
Upgrade Port

Item

Location

Operation temp,

Storage temp,

Operation humidity

Condition

Indoor
-10°C to 55°C [14°F to 122°F]
-25°C to 70°C [-13°F to 158°F]
Non condensation,5% R.H. to 80% R.H.

Power connection

WiFi router connection ready (Soft AP)

WiFi router connection ready  

The connection attempt to the Cloud

Device Authentication after the Cloud connect

Equipment installation complete

Firmware Update

ON

ON

OFF

BLK

OFF

GLOW

BLK

BLK

OFF

OFF

OFF

OFF

OFF

BLK

OFF

상태

LED

LEFT

CENTER

RIGHT

Wall mount : 4mm hole, 2EA

46mm

68mm

CTs are connected to this terminal. The terminal must meet the correct side of CT to 
measure power correctly.

 Example of CT wiring 

◇  Wiring with a CT should follow the direction of CT that power line side is at S1(   ) of CT and Load 