QUICK ASSEMBLY GUIDE 

PV-3

HELIOMOTION

HelioZenit

 

Revision 1, 2021

Summary of Contents for HELIOMOTION PV-3

Page 1: ...QUICK ASSEMBLY GUIDE PV 3 HELIOMOTION HelioZenit Revision 1 2021 ...

Page 2: ...1x 1x PART I FOUNDATION ...

Page 3: ... should be at least 65x65 cm 70 cm deep 300 liter Push the rod unit into center of the concrete and let the flange rest on top of the concrete Use a spirit level to align the flange horizontally Allow the concrete time to harden before assemling the remainder of the power plant The concrete can be covered with sand after it has cured for 2 weeks Soil founda on ...

Page 4: ... template Make the holes 20 mm wide and 250 mm deep Use compressed air to remove any debris and water from the holes to ensure a clean bonding surface Fill the holes 2 3 full with chemical anchor adhesive 400 500 ml Push the rod unit into the holes and give the adhesive time to cure before continuing the assembly Bedrock foundation ...

Page 5: ...e accurate than a regular compass 3 Align the phone to true south or north according to the compass 4 Rotate the column so that the edge of the tube lines up with the edge of the phone Make sure the compass is not distorted by being too close to any metal objects This alignment can be fine tuned after the installation is complete and the tracker has turned towards the sun 4 5 Adjust bottom nuts to...

Page 6: ...1x 1x 6x 4x PART II TRACKER ...

Page 7: ...6x 4x 1x 1x 1 2 ...

Page 8: ...2x 1x 1x 4x 2x 6x 4x 1x 2x PART III FRAMEWORK ...

Page 9: ...4x 2x 945mm X X 2000mm 945mm X Panel width 3 2000 2 2x 22mm 2x 2x 22mm 2 1 ...

Page 10: ...592mm 592mm 1x 4x 1x 4x 4 3 ...

Page 11: ...1x 1 Tighten these nuts slightly 2 6 5 ...

Page 12: ...3x 16x 16x 12x PART IV PANELS ...

Page 13: ...e with four panel clamps C Remove the extension rod and attach only the black angle rod Make sure to prevent the panels from swinging downwards when changing the rod Leave both fork joints F and one of the clevis eye mating pieces E unscrewed half a turn to allow for full range of movement Make sure to bend both retaining pins so that the fork joint bolts are held in place ...

Page 14: ...tandard applications are listed below String inverter Grid tied string inverters generally supports a high voltage PV input Therefore all 3 panels are typically connected in series when using a string inverter Microinverter Grid tied microinverters typically have 1 2 or 4 PV inputs Mount the microinverters M and a junction box J similar to the illustration below so that they are easy to connect to...

Page 15: ...AC U must be connected by a certified electrician However preparation work may be done by a layman as long as local code requirements are followed AC wires must be at least 1 5mm thick and use an outdoor cable Be mindful of the AC labels and wire colors Neutral N is blue Phase 1 L1 brown Phase 2 L2 black Phase 3 L3 gray and ground G green yellow If using a 1 phase system the electrical wiring can ...

Page 16: ...ground are properly attached and protected so the cable cannot be accidentally moved or damaged Sections coming out of the ground need to be protected by for example a metal U profile 4 Fill out and attach the included self adhesive warning labels These labels need to be provided near the solar installation the fuse box and the utility meter to indicate the presence of on site generation and the p...

Page 17: ...allation the junction box K can be wired as shown above If the string inverter is placed on the column of the solar installation the 24VDC transformer can be added to the outdoor junction box K along with AC breakers Grid ed system with string inverter K G PV x2 Ground G G DC x4 G 24VDC 2x1mm K A ...