background image

SERVICE- INSTRUCTION

Publications-No.:

599 47 22-58/4

replaces 

599 47 11-18/1

T.D. RS 05/2000

Language: English

AES II- Absorption Refrigerators

(only for built- in in motor caravan)

COOLING

3110

RM 4185

RM 4215

RM 4235

RM 4265

RM 4275

RM 4285

RM 4365

RM 4405

RM 4505

RM 4605

RM 4705

RM 4805

RM 5215

RM 5275

RM 5405

RM 6275

RM 6295

RM 6365

RM 6405

Summary of Contents for EFC 6405

Page 1: ...1 18 1 T D RS 05 2000 Language English AES II Absorption Refrigerators only for built in in motor caravan COOLING 3110 RM 4185 RM 4215 RM 4235 RM 4265 RM 4275 RM 4285 RM 4365 RM 4405 RM 4505 RM 4605 RM 4705 RM 4805 RM 5215 RM 5275 RM 5405 RM 6275 RM 6295 RM 6365 RM 6405 ...

Page 2: ... Technical Descriptions 5 3 1 Block Diagram 5 3 2 Power Module Connections 6 3 3 Display Module 7 3 4 Power Module 8 3 5 Ignition Device 8 3 6 Thermocurrent Adapter 8 4 0 Installation 8 5 0 Troubleshooting 8 5 1 Diagnostics Mode 8 5 2 Error Analysis and Elimination 9 6 0 Wiring Diagram 11 7 0 Spare Parts Numbers 12 8 0 Service Bulletins 13 9 0 Operation of AESII with solar 17 charging regulators 2...

Page 3: ...lls below the relevant limit values 200 V for mains power supply voltage and 11 V for battery operation gas operation is selected see low voltage operation For its operation the AES II refrigerator requires a 12 V continuous plus supply to operate the control electronics Operation on a 24 V power supply is not possible 2 1 Priorities The refrigerators selects the type of energy according to the fo...

Page 4: ...does not begin operating the refrigerator on gas until the motor has been turned off for 15 minutes to avoid an undesired switchover to gas operation during a tanking procedure 2 5 Thermostat Sensor The thermostat sensor consists of an electrical resistor NTC The resistor is installed on the evaporator cover but it does not have a direct connection to the evaporator coil The purpose is to measure ...

Page 5: ...scriptions 3 1 Block Diagram The following diagram shows the AES II system components 5 Display Modul Power Modul Solar input 230 V 12 V D generator Reigniter Thermocurrent adapter Heating element DC Heating element AC ...

Page 6: ...splay power module P2 I Temperature sensor P3 I O Reigniter P4 O Lifting magnet T1 O 12V DC lighting T2 O 12V DC heating element T3 I 12V DC power supply T4 I 230V AC T5 O 230V AC heating element T6 O 230V AC heating element T7 I 230V AC T8 I Ground T9 I Generator D T10 I Solar system ...

Page 7: ... switch to switch the refrigerator off and on again Important If there is a fault during gas operation and you don t notice it before the refrigerator changes to 230 V for example due to a priority change the AES LED B again changes to green until the cooling function has been established again However the next time it wants to change to gas operation the fault is displayed again and gas operation...

Page 8: ...ls the thermocurrent adapter The adap ter serves to switch off gas operation during the chan ge from gas to another operating mode by interrupting the thermocurrent to the ignition fuse 4 0 Installation To guarantee the orderly functioning of the AES II refrigerator correct electrical installation is absolutely necessary The 12 V connection to the battery must be a 2 pole connection The connection...

Page 9: ...re controlled LED 4 12 V operation 12 V heating cartridge is controlled LED 5 Ignition device is controlled Important For safety reasons it is possible to control the lifting magnet just once If the lifting magnet is controlled again you must first switch the device off and then start diagnostics operation again C Terminating diagnostics operation You can use the power switch at any time to switch...

Page 10: ...fuse down deeply enough so there is no mechanical contact in the magnetic insert Elimination 5 To check after tightening the lifting magnet press down on the red ignition fuse button If the flame stops after the lifting magnet drops the lifting magnet or the ignition fuse must be adjusted In the factory setting the AESII electronics control the lighting If there is a lighting defect first check th...

Page 11: ...6 0 Wiring Diagram 11 ...

Page 12: ...0 1043 02 3 AESII electronic 295 1876 10 7 3 amp AC fuse 294 3541 00 9 20 amp DC fuse 210 6389 10 5 Lifting magnet 295 1151 00 6 Temperature sensor cpl 295 2072 00 3 wih cable Old version of the reigniter Fa Cramer 295 1654 10 8 New version of the reigniter Anstoss Company 295 2368 00 5 Bulletin 599 4716 54 5 Note page 13 and 14 ...

Page 13: ...13 8 0 Bulletins ...

Page 14: ...14 ...

Page 15: ...15 ...

Page 16: ...16 Publication No 599 4721 91 7 Service 99 02 03 B O K V ...

Page 17: ...red to as on board power supply as this would result in continuous 12V operation of the refrigerator and the battery would be completely discharged in a very short time The solar input of the AES has a function similar to the D input which will only allow 12V operation with the motor generator running and if sufficient power is available for 12V operation Due to the high current flow required for ...

Page 18: ...r AES has 12V level refrigerator with 12V operation AES has 0V level normal operation 220V gas or 12V with motor running Refrigerator with AES Terminal block on top of refrigerator Connecting diagram for AESII operation with solar regulator and AES switching output Shared connection for battery and on board power supply ...

Page 19: ...19 Electrolux Siegen GmbH In der Steinwiese 16 D 57074 Siegen Tel 0271 692 0 Fax 0271 692 300 ...