ZXG10 iBSC Hardware Installation Guide
Figure 7-12 Install O-Type Seal
5.
Separate the front part of the feeder connector from the rear part, and insert the feeder
into rear connector till it contacts the first feeder corrugation. Turn it left and right, so
the outer conductor of feeder expands and contacts the rear connector. Finally, the
rear connector is aligned into the first trough slot for outer feeder conductor, as shown
in
.
Figure 7-13 Install Rear Feeder Connector
6.
Fix the front connector onto the rear connector. After it is in the correct place, use
the proper spanner to fix the front feeder connector and keep no any relative rotation
between the rear feeder and feeder. Use the spanner to fasten the front feeder
connector. The recommended torque is 7~10 N.m. The fixation process is shown in
7-12
SJ-20110531095035-004|2011-10-28 (R2.0)