Outdoor Prepackaged System Installation Instructions

  1.  Review the drawing in Fig. 3 on page 8 and the actual system to 

become familiar with the components in the packaged grinder pump 

system.  Review where the unit will be installed.  Determine where 

the power feed, inlet pipe, and discharge pipe will be located.

  2.  Remove the unit from packing.  Prepackaged outdoor systems are 

preassembled at the Zoeller Company and require a minimum of 

field assembly work.  Float switches are set and tethered for proper 

operation from the Factory.  Systems using an automatic unit, WD 

or WH series, have an integral “on/off” float switch.  See Fig. 4 

on page 5 for adjustment instructions.  The alarm switch should 

be located 3” above the pump “on” level.  Three float systems 

used with a control panel are placed at 27”, 24”, and 15” from the 

bottom of the basin.  Four float systems used with a control panel 

are placed at 33”, 27”, 24”, and 15” from the bottom of the basin. 

If the invert location is at or below the level of the float switches, 

contact the factory.  

  3.  Float switches are tied in place for shipping purposes on all model 

prepackaged systems.  Cut the cable tie around each float switch 

bulb or the unit will not operate properly.  Verify that where the 

float switches are set will work for your application. 

 

Verifying 

that the float switches are set properly and will not hang up 
inside the basin is the responsibility of the installing contractor. 

  4.  Dig a hole for the basin.  The hole should be at least 24” larger in 

diameter than the basin diameter to provide 12” of backfill all around 

and deep enough to provide either 12” of compacted backfill or 6” 

when a concrete pad is required.

  

Note:  Care must be taken when 

excavating in order to avoid underground utilities and disturbance of 
existing structure foundations.  The hole should be located at least ten 
feet from adjacent structures.  Additional distance may be required to 
sufficiently locate the basin outside of the loading area of the adjacent 
structures.

 

5.  Determine the location of the inlet hub based upon your inlet pipe 

arrangement.  The inlet hub must be used with 4” pipe.  It is best to 

install the inlet on the side of the basin opposite the float switches.  
Most systems are supplied with a field installed 4" pipe seal inlet 
fitting.  This inlet fitting is installed in the basin's side-wall in a 5" 

hole drilled with a hole saw at a location lining up with the inlet 
pipe.

  6.  The bottom of the excavation can now be properly backfilled, 

compacted and leveled.  Set basin in hole.  Ensure the removable 

cover extends above the finished grade line and the grade slopes 

away from the unit.  Backfill and subbase should be 1/8” –3/4” pea 

gravel or 1/8” –1/2” crushed stone.  (Reference basin installation 

instructions included with unit.)  Connect the 4” inlet pipe to the 

inlet hub.  

  7.  Pouring a concrete anchor around system can now be completed.  

Basin should be filled with water when pouring concrete to minimize 

movement of the system.  Backfill around basin with specified media.  

Care should be used to avoid damaging components or leaving voids 

when back filling.  Refer to Basin installation reference guide on 

more specific requirements.

  8.  PVC or HDPE discharge piping is connected to the 2” threaded 

fitting located in the basin sidewall.  Support discharge piping with 

sufficient backfill.

  9.  Connect lift cable to top of pump.  Lower the pump into basin ensuring 

the discharge pipe bracket slides into the disconnect fitting.

 

10.  Note:  The grinder basin is a sewage holding tank.  Vent connection should 

be installed in accordance with all national, state and local plumbing 
codes.

  11.  Dig a trench for the electrical conduit.  The conduit should be located 

below the frost line.  Follow all applicable electrical codes.

  12.  If using a junction box, connect the electrical conduit and wiring 

according to instructions included in this manual and wiring diagram 

in box.  If a potting kit is provided with the junction box,  follow the 

instructions for sealing the conduit connection to the junction box. 

If a potting kit is not provided, the conduit connection to the junction 

box must be sealed.

 13.  Mount the control panel within sight of the system.  Connect 

float switches and pump cords according to the “Pump Wiring 

Instructions” found later in this manual and located inside the panel 

enclosure.

  14.  Remove any debris from the basin.  Using clean water, check the 

system for proper operation.

 15.  Seal and secure the lid using the proper bolts and sealant when 

using a lid without a formed gasket. 

  16.  Test system for leaks and proper pump operation.
  17.  Record system start up data for future reference.

This set of instructions is for factory prepackaged outdoor grinder systems only.  If this is a field assembled outdoor system 

you can use these instructions as a guideline.  If this is an indoor system then go back to pages 6-7 in this manual that covers indoor systems.

Summary of Contents for BA840

Page 1: ...ause serious personal injury death or major property damage Warns of hazards that CAN cause personal injury or property damage INDICATES SPECIAL INSTRUCTIONS WHICH ARE VERY IMPORTANT AND MUST BE FOLLOWED THOROUGHLY REVIEW ALL INSTRUCTIONS AND WARNINGS PRIOR TO PERFORMING ANY WORK ON THIS PUMP MAINTAIN ALL SAFETY DECALS PUMPSWITHTHE US MARKARETESTEDTOULSTANDARDUL778 CSA CERTIFIED PUMPS ARE CERTIFIE...

Page 2: ...tinuous service during unusual conditions Recommended Limits of Application 800 Series Grinder Pumps These recommended application limits are for pump stations pumping to a gravity main Low pressure pipe systems should be designed with a pump located at each house For applications where a lift station would handle between 15 and 60 homes consider the 71 Series grinder pump which is available throu...

Page 3: ... other pit peculiarities and are secured so that the grinder pump will shut off It is recommended to use rigid pipe and fittings and the pit be 24 in diameter for simplex systems and 36 in diameter for duplex systems or larger 4 Grinderinstallationsshouldbecheckedyearlyfordebrisand orbuild up which may interfere with the ON or OFF positions of variable level float control switches Repair and servi...

Page 4: ...tem installation 3 All electrical connections including pump to control box and power supply to control panels must comply with the National Electrical Code and applicable local codes Conduit and panel enclosure openings must have a gas and watertight seal Installation of electrical panels conduit and connections should be made by a qualified licensed electrician A UL Listed potting kit P N 10 235...

Page 5: ...RELAY START CAPACITOR GREEN RED WHITE BLACK BLUE ORANGE MOISTURE SENSOR TERMINALS WHITE BLACK 14 6 18 2 REVERSE MOTOR ROTATION BY INTERCHANGING ORANGE WIRE WITH RED WIRE L2 RUN CAPACITOR GROUND SCREW 2 1 5 COMPONENT LAYOUT PUMP START RELAY START CAPACITOR RUN CAPACITOR RED WHITE ORANGE BLACK MAIN START PROTECTOR BLACK WHITE L1 L2 T2 T1 230V AC OR 208V AC CONTACTOR BLUE 2 1 5 SINGLE PHASE MODELS 84...

Page 6: ...d Indoor Prepackaged System FIGURE 5 All installations must comply with all applicable electrical and plumbing codes including but not limited to the National Electrical Code local regional and or state plumbing codes etc SK1695 36 48 60 24 NOMINAL ...

Page 7: ...rly 5 Dig a hole for the basin The basin should be located in a very low traffic area within 15 of the power disconnect The hole should be at least8 largerindiameterthanthebasininordertoleave4 ofbackfill all the way around the perimeter A minimum of 4 of compacted subbase is also required Backfill and subbase should be 1 8 to 3 4 pea gravel or 1 8 to 1 2 crushed stone Also reference the basin inst...

Page 8: ...GLASS AFD 1 25 2 Z RAIL 2 CAST IRON CHECK VALVE 3 4 GUIDE RAILS 2 SCH 80 BALL VALVE 2 FLEX BOOT FITTING LOCATION VARIES WITH BASIN DEPTH FLOAT TREE ASSEMBLY 2HP GRINDER PUMP 2 PVC SCH 80 PLBG 1 8 302 STAINLESS STEEL LIFTING CABLE ALARM ON OFF SOLID FIBERGLASS COVER HIGH WATER ALARM OR SIMPLEX CONTROL PANEL FIELD INSTALLED ALARM FLOAT SWITCH MUST OPERATE OFF LOW VOLTAGE TO BE USED WITH QWIK BOX SK3...

Page 9: ...n the basin s side wall in a 5 hole drilled with a hole saw at a location lining up with the inlet pipe 6 The bottom of the excavation can now be properly backfilled compacted and leveled Set basin in hole Ensure the removable cover extends above the finished grade line and the grade slopes away from the unit Backfill and subbase should be 1 8 3 4 pea gravel or 1 8 1 2 crushed stone Reference basi...

Page 10: ... installed Floats positioned properly Discharge valves open 3 16 vent hole drilled in pipe between check valve and pump Once the above has been verified proceed with the following checks Pump power cables and control floats properly installed and voltage verified Conduit connections to panel and junction box are properly sealed After installing the pump into the containment area with adequate subm...

Page 11: ...nd remove the spacer shims located behind the star cutter 5 Remove the three cap screws holding the disc and remove disc from the pump 6 The disc and star cutter can be replaced with new service parts or resurfaced by grinding Resurfacing is accomplished by surface grindingbothdiscandstarcuttertoa32microfinish Donotattempt grinding in the field Send parts to a qualified machine shop or return to t...

Page 12: ...Service Checklist Electricalprecautions Beforeservicingagrinderpump alwaysshutoffthemainpowercircuit Makesureyouarewearing insulated protective sole shoes and not standing in water Under flooded conditions contact your local electric company or a qualified licensed electrician for disconnecting electrical service to the pump prior to removal Grinder pumps contain oil which becomes pressurized and ...

Reviews: