It must be positioned after the heating and the filter.
This must be
the last fitting before the inlet.
The cell must be horizontal : The water input and output will be pointed
downwards.
Water can circulate in both directions.
For the gluing : the pipe unions are in moulded ABS polymer.
They can be glued to the PVC pipes using a suitable PVC glue.
First of all clean the surfaces to be glued with a solvent and then glue.
Hold in position for at least 30 seconds.
If you choose to install the cell with a bypass routing, we recommend
that you use a non-return valve and not a manual valve between
the CLEARWATER® and the inlet.
Important :
> The water pressure in the cell must not exceed 2 bars.
> The water temperature must not exceed 40°.
> If you choose to install shut-off valves, stop the pump then the
CLEARWATER® system before handling the valves. No current must reach
the electrodes when the valves are closed because this can damage
the cell. Make sure that the valves are open again before re-starting
the pump and the CLEARWATER® system.
Fix the control box to a wall within 1.5 m from the cell and 1.2 m above
the ground, respecting safety regulations in terms of the distance from
the pool (this must be at least 3 metres from the edge of the pool).
If the control box is installed on a pillar, it must be placed on a flat
and watertight panel at least 24 cm wide and 44 cm high.
Do not enclose the control box in an outer shell.
Do not install it above a source of heat.
It is preferable, but not essential, to place it in a shady area, sheltered
from the rain and direct sunlight.
Connect the power cable to the electrode terminals.
Blue with blue and black with black.
Make sure that the connections are firmly attached.
Connect the electric cable from the CLEARWATER® electrolyzer’s control
panel to the clock in the switch cabinet that controls the pump
(servo-system from the electrolyzer to the pump).
Wait 24 hours to allow the PVC glue to
set perfectly on the cell’s connections.
15/LM2
Installation of the cell
Installing the control box
How to connect
the control box to the cell
How to connect
the control box to the pump
Electric control panel with clock
Pump