- 5 -
3.2
、
UNLOADING WARNNING
3.2.1 Use a suitable lifting fixture to handle, no more
than 2 pallets of modules. Before lifting, check whether
the tray and the carton are damaged and whether the
hoisting ropes are strong and firm. Two people shall
support at the two sides of the righting carton gently to
place it on the relatively flat position of the project site.
3.2.2 Use a forklift to remove the module pallets from
the truck
.
3.2.3 Put the modules on level ground.
3.2.4 Do not stack the modules at the project site.
3.2.5 Store the module in a dry and ventilated place.
3.2.6 Cover the module with waterproof material to
prevent it from moisture.