Page 10 of 28
804050US v1.27 06.21 CS175 Install Instruction
Section 2
Ventilation
Cool air IN via
front vent grille
Warm air OUT via
kickboard grille
**MIN. 100mm
(4”)
2.2 Recommended Installation Diagram
When installing air flow ducts, the following tools will be required:
•
Jigsaw and a 12mm (½”) Drill
•
Keyhole or Wall Board saw.
2.1 Ventilation for All Models
Proper air circulation must be provided for all models. The system will operate correctly only if the
recommended air gaps are achieved during installation.
IMPORTANT: Allow a minimum clearance envelope of 50mm (2”) either side, and 200mm (8”)
above the Command Center.
The vent duct and louver panels must be installed for all under floor and /or door vent systems, as instructed.
**Note: Inlet and outlet vents should be separated by a minimum of 100mm (4”), to avoid hot air
recirculation.
!