Installation manual

Connecting the handrail or mid rail:

The handrail and the mid rail are extended by attaching 
the individual elements to each other, one after the other.

Attention! 
Please ensure that the plug connectors are inserted as far 
as possible.

The connector is permanently 
secured using a drilling screw.

Corner:

Insert the cast joint into the handrail / mid rail, in each case 
pre-drilling a bore hole with a diameter of 3.5 mm approx. 
15 mm from the edge, and fix the joint with self-tapping dril-
ling screws. We recommend fixing the cast joint on one side of 
the rail before mounting the rail, in order to prevent anything 
dropping to the ground (roof edge!). 

Assembled corner joint with maximum permissible 
dimensions

The distance from the joint to the post is max. 0.44 m 
on the one side and max 1.65 m on the second side.

max. 0.44 m

max. 1.65 m

Step 8: Installing the toe boards 

This step is only necessary if the distance between the working 
surface and the upper edge of the parpet is less than 15 cm.
Please ensure that the space between the lower edge of the 
toe board and the surface of the substrate is always less than 
20 mm. There are two types of mounting here, depending on 
the height of the green roof build-up; 
Case 1: Using the upper slotted hole at the post foot

for a post at 90° angle

for a post at 67.5° angle

Insert two hammer head bolts per 

 

post into the lower T-groove of the 

 

toe board, thread into the slotted  

holes of the foot of the post, fit the 

 

nuts and tighten. 

Step 7: Install the green roof to provide 
           static equilibrium

In line with the instructions at the start of this document on 
providing static equilibrium by means of the green roof, the 

green roof is to be installed across the entire roof. In doing 

this, the green roof will also cover the counterweight base 
plate of the post foot, therefore providing the required ballast! 

Case 2: Using 2 metal brackets per post
Where the green roof build-up is accordingly high, the toe 
board is fixed directly to the guardrail post. 

Insert four hammer head bolts into the T-groove of the toe 
board and insert into the drill holes of the metal brackets on the 
post. Then, fit the nuts and tighten.  

Insert four hammer head bolts into the toe board guide, insert 

into the holes of the butt or corner connector, fit washers and 

nuts and tighten.  

Connecting toe board and corner piece

Summary of Contents for Fallnet ASG

Page 1: ...Fallnet ASG Installation maintenance and user manual for the Fallnet ASG maintenance guardrail ...

Page 2: ... 6 Maintenance storage and Page 7 disposal User manual and Page 8 manufacturer s specifications Assembly 7 Install the green roof to provide static equilibrium 4 5 Lay the protection mat Install the post module 1 2 Loosen transport safety device Position the post at the required angle 3 Fix the position of the post Maintenance guardrail Fallnet ASG ...

Page 3: ...e mid rail is 0 3 m here The handrail or the mid rail can be extended by locking one element into another The connectors are to be inserted as far as possible The connectors for the handrails mid rails and corner connectors are secured with a drilling screw Corner joints are to be used for the corners of the handrail and mid rail The distance between the corner joint and the post is max 0 44 mm on...

Page 4: ...olt Step 2 Place the post at the required angle Draw up the post to 90 and insert the screw Draw up the post to 67 5 and insert the screw Step 3 Fixing the posts for a post at 90 angle for a post at 67 5 angle Fit washer and nut and tighten Fit washer and nut and tighten Step 4 Installing a protection mat on the roof Regardless of the required angle of the post on the guard rail a protection mat w...

Page 5: ... less than 15 cm Please ensure that the space between the lower edge of the toe board and the surface of the substrate is always less than 20 mm There are two types of mounting here depending on the height of the green roof build up Case 1 Using the upper slotted hole at the post foot for a post at 90 angle for a post at 67 5 angle Insert two hammer head bolts per post into the lower T groove of t...

Page 6: ...o zinco greenroof com www zinco greenroof com 6 Installation manual Layout example The height of the attica has to be at least 150 mm above the upper edge of the working area otherwise toe boards are to be installed max 0 44 m max 1 65 m max 0 44 m max 1 65 m Attention The roof pitch must not exceed 5 max 2 60 m ...

Page 7: ...condition is to be maintained In addition to checking the static equilibrium the guard rail system is to be checked once a year to ensure that it is complete and that the connections are tight and to check for possible corrosion Defective or missing components are to be replaced Loose connections are to be tightened Disposal Where they are no longer required the components of the ZinCo Fallnet ASG...

Page 8: ...ASG collective edge protection system offers the advantage that it protects everyone working on a roof without them having to take special measures The user is to be instructed to carry out the following visual and manual checks prior to starting work at the edge of a roof visual check of the visible parts e g for deformation corrosion visual check of the ballast depth Evidence of restricted funct...

Reviews: