Assemble the mount as follows: 
 

 

Assemble the mount (without the load cell) as shown in picture 1, taking care that the top and 
base plates are correctly aligned (vertically). 

 

The top plate (see drawing and Part List pos. 10) 
should be locked at installation height using the socket 
head counter sunk bolts (pos. 9) and the upper nut 
(pos. 7, see picture 1).  

Note:

 the long bolts must not protrude above the top 

plate. This can cause weight on the long blots and that 
will distorts the measured value. 

 

Then the socket head counter sunk bolts (pos. 9) 
should be locked securely by turning the thin nut (pos. 6)    

 

 

 

   

Picture 1

 

downwards to the base plate (pos. 1). 

 

 

Then the mount is ready to install in the application of the customer. 

 
Installation 

Important to know is to install multiple mounts in such a way that all bottom plates are at the same 
level and in the same horizontal plane. The same goes for the top plates. Always use shim plates to align 
mounts in the same horizontal plane and level. Always check that load cell and/or mount are not loaded 
with forces exceeding their specifications. 
 
Install as follows: 

 

Locate the mount into the application and secure using the four lower and two upper 
fixing holes. Two hexagon bolts (1 upper and 1 lower) should be used to secure the earth cable 
(shown in Part List drawing pos. 14-15) 

 

Coat both bearing load surface (pos. 13) (see picture 2

) with ‘high pressure’

-grease and locate 

the rocker pin support . Insert the rocker pin with lower bearing (pos. 11) in the load cell (see 
picture 3) and slide the load cell into place, ensuring that the rocker pin (pos. 13) is properly 
located (see picture 4). 

 

Place the load cell in the mount by putting it between the bottom plate and top plate in a half 
turned position and put it upright ensuring that the rocker pin is properly located in the right 
position 

Warning:

 For safety reasons, always use a tool to align the rocker pin if necessary during 

this process, don’t eve

r use your hands.  

 

Secure the load cells with the bolts (See Table 2) (pos. 3). Make sure that the washers (pos. 3 & 
4) are placed and that the correct torque (see Table 1) on the bolts is used (see picture 5). 
 

Description: 

Dimensions 5 

 200kg 

Dimensions 250 

 500kg 

Hexagon screws to fasten load cell 

M8 x 45 

M10 x 50 

Socket head countersunk screws 

M8 x 40 

M8 x 40 

Bolts to fasten the earth cable 

M6 x 6 

M6 x 6 

Table 2 