3.3.1.2  Resetting the filter maintenance display 

The filter maintenance indicator must be reset after each air filter change in order to restart the filter maintenance cycle 
monitoring. To do this, touch the (+) and (-) keys on the control panel simultaneously for three seconds. The flashing red 
filter maintenance LED will go out. 

NOTE

 

As part of filter maintenance for units with a second room connection, check any other air filters that may be present in 
the ventilation system. 

 Unit 

maintenance 

Maintenance of the unit is limited exclusively to the external surfaces of the ventilation unit and the operating surface of 
the control panel, which should be wiped down from time to time using a soft, damp cloth – never just wipe dry. 

 

WARNING

 

Risk due to electric shock 

Disconnect the ventilation unit from the power supply before cleaning. 
Make sure that no moisture can enter the inside of the housing during cleaning. 
Never use a high-pressure cleaner, steam cleaner or steam jet.

 

 

NOTE

 

Never use flammable, acidic, corrosive or abrasive cleaning agents. 

  What should I do in case of a malfunction? 

In the event of a fault message (indicated by the LED fault lighting up continuously), contact customer service. 
Information about the type of your ComfoSpot 50 can be found on the type label, which is located under the design cover 
of the unit. 

NOTE

 

As a reaction to a fault status, the fans are shut down. 
As soon as there is a disconnection, the apartment will no longer be mechanically ventilated. This may result in moisture 
and mould problems in the room that requires ventilation.  

Chapter for qualified personnel 

 Installation 

requirements 

The following requirements must be assured for the correct installation: 

 

Installation in accordance with the general and locally applicable safety and installation regulations from, among others, 
the electric utility, and in accordance with the regulations stipulated in this manual. 

 

Outside wall with final construction thickness of minimum 335 mm. 

 

Sufficient space from objects and for maintenance work (at least 10 cm on extract air side, 20 cm on the supply air 
side, 70 cm at the front, and 2 cm above the unit), with regard to the housing surfaces when installed. 

 

Minimum distances on the facade side of 10 cm for outdoor air and 20 cm for exhaust air; rrecommended suction 
opening for the outdoor air with respect to the ground >1 m, however, at least unpolluted air in the suction area t. 

 

Electrical connection for stationary units for a working voltage range between 100–240 VAC / 50–60 Hz. 

  Packaging and handling 

The ventilation unit and the facade finish are packed in a transport-safe box. Proceed with care when unpacking and 
handling the ComfoSpot 50. 

NOTE

 

Do not damage or dispose of the packaging before final installation of the ventilation unit. 

  Checking the scope of delivery 

If damages or incompleteness should be determined at the delivered product, please contact the supplier immediately. 
Included in the scope of delivery are: 

  ComfoSpot 50, including installation kit 

  Facade finish including installation set 

 User 

manual 

  Product labels for energy-efficiency label 

Summary of Contents for ComfoSpot 50

Page 1: ...Decorative Radiators Comfortable indoor ventilation Heating and cooling ceiling systems Clean air solutions User manual on operation and installation for operators and installers Zehnder ComfoSpot 50...

Page 2: ...property of Zehnder Group Publication as a whole or in parts requires the written approval of Zehnder Group In house duplication designated for the evaluation of the product or for proper use is permi...

Page 3: ...ements of the control panel 6 Description of the operating functions and signals 7 Options for ventilation operation 9 External control panel 9 Operation via networking 9 Automatic operation via senso...

Page 4: ...iciently qualified for the respective work involved Qualification of target group 1 3 1 1 Users Users must be instructed by qualified personnel as follows Instruction in hazards when handling electric...

Page 5: ...supply unless instructions to the contrary are listed in the manual Following installation all parts that could lead to personal injury are protected by the housing The unit cannot be opened without...

Page 6: ...acade finish Intended use also includes observing all instructions in the user manual In the event of improper use the Zehnder Group accepts no liability for any damage that may occur and no warranty...

Page 7: ...unit fully automatic demand controlled ventilation operation is possible An enthalpy exchanger which can transfer both humidity and heat owing to the physical characteristics is used in the ComfoSpot...

Page 8: ...l has touch sensitive buttons and LED status indicators NOTE The ventilation unit can be operated at the same time with the internal and the external control panel Item Description A Facade finish ext...

Page 9: ...up Fan speed 3 FS3 Increased ventilation The ventilation unit runs at a higher ventilation level 40 m h to reduce peak loads e g when several people are present LED1 4 light up Fan speed 4 FS4 Intensi...

Page 10: ...e LED display is switched off If any key is touched the LED indicator will be activated again Touching the button brings about no change to the operating mode however Standby mode The unit can be swit...

Page 11: ...s switched off Display of LED1 3 as example Frost protection mode From an outside air temperature of 4 C the frost protection function is automatically activated In frost protection operating mode the...

Page 12: ...ting mode with humidity control 3 2 3 2 Functional principle of CO2 VOC sensor NOTE The CO2 sensor module and the VOC sensor module are each combined with a humidity temperature sensor The CO2 sensor...

Page 13: ...unit is equipped with two air filters of filter class ISO Coarse 70 as standard Retrofitting with filters of filter class ISO ePM10 80 is possible preferably the higher quality ePM10 filter is inserte...

Page 14: ...the bottom cover of the interior cover next to the filter compartment in each respective case Make sure that the filter is not pushed into the filter compartment with force 7 Insert the filter caps a...

Page 15: ...onger be mechanically ventilated This may result in moisture and mould problems in the room that requires ventilation 4 Chapter for qualified personnel Installation requirements The following requirem...

Page 16: ...rge when handling the control unit e g by wearing an anti static armband Installation preparations 4 2 2 1 Preparations for installing the wall mounting pipe Prior to installing the ventilation unit a...

Page 17: ...unit either to the wall thickness or to the measure of length of the wall mounting pipe by shortening the EPP housing extension NOTE The cut must be performed all around perpendicular to the axis of t...

Page 18: ...the openings for the electrical connections and fix the bottom cover of the interior cover in place using the screw from the installation set or the alternatively selected fixing material Relocating...

Page 19: ...control panel carrier Restore the plug connection between the ribbon cable and control panel NOTE Watch out for the reverse polarity protection for the post connection when connecting 6 Install the ri...

Page 20: ...Der The power supply is connected after the final positioning of the unit in the wall mounting pipe In doing so proceed as follows 1 Plug the WAGO lighting terminals 3 pieces included in the installa...

Page 21: ...mounting material suitable for the facade construction The professional and safe installation is to be checked and the responsibility of the technical crew performing the work NOTE The exterior wall p...

Page 22: ...ten the four screws from the supplied installation kit for the top cover of the outside wall panel on the bottom cover of the outside wall panel NOTE In general the top cover of the outside wall panel...

Page 23: ...ing pipe until the PVC cover for the control board is freely accessible 5 Remove the PVC cover of the control board at the side of the ribbon cable entry out of the slot on the EPP housing and grippin...

Page 24: ...EPP housing tight when doing so 10 Following the inspection install all parts whilst considering the restoration of all electrical connections in the reverse order 11 Restore the power supply and set...

Page 25: ...ension set Mounting position Horizontally in the wall mounting pipe air passage openings laterally vertical on the interior cover and outside wall panel thumb wheel for shutter adjustment AT THE RIGHT...

Page 26: ...370 330 Bottom cover for outer panel View from outside EHA ODA 330 360 Angular structural shell set View from outside Angular structural shell set View from inside 40 areas for cable entry 35 90 4x fa...

Page 27: ...25 Terminal scheme...

Page 28: ...ehnder Group Deutschland GmbH Almweg 34 77933 Lahr Deutschland T 49 7821 586 392 F 49 7821 586 406 sales international zehndergroup com www international zehnder systems com PDE Manual_CS50_V4 0_V0621...

Reviews: