Chapter 5 – Recommended Regular System Maintenance
We recommend that the system be operated in Test Mode at least once per week, to check for proper
spray nozzle atomization, correct overall spray pattern, and for any fault code activations. For reference,
the following is a reference for using Test Mode to verify correct system operation:
Test Speed:
8 km/hr (5 MPH)
Flow Rate (both spray booms on):
54 L/min (14.3 GPM)
Spray Pressure:
138 kPa (20 PSI)
Scaling Factor:
100%
The water filter should be purged using the removable cap once per week, and the filter element should be
inspected for debris once every 2 weeks.
Also, we recommend that the Ice Making Water tank be fully drained and rinsed out once every 2 weeks
to ensure proper system performance.