BUILD METHOD

9

Fit Fixed Decks between towers. Ensure all 

wind locks are engaged.

10

Fit Toe Board Brackets, Side Toe Boards and End 

Toe Boards (see image below) to the working level.

Fit 615 LG Infill Decks and 323 LG Infill Decks (see 

detail on the right) to the working level.

Remove all Guardrail Frames from the BoSS 

Infinity Multipurpose frames. Move Stabilisers so 

that they are parallel to frames.

The build is now complete.

To dismantle the tower:

Simply follow the assembly steps in reverse, 

ensuring that the 3T method is followed.

FILE: S140105

Drawn: 29/01/2015

Page: 12 OF 14

Issue: A

LINKED PREFABRICATED TOWER SCAFFOLD - LADD 3T

FILE: S140105

Drawn: 29/01/2015

Page: 12 OF 14

Issue: A

BoSS IS A REGISTERED TRADEMARK OF YOUNGMAN GROUP LTD

© 

YOUNGMAN GROUP LTD - 29/01/2015  

FOR UP TO DATE INFORMATION ON THIS PRODUCT CHECK

www.youngmangroup.com/brands/BoSS-towers  

Summary of Contents for Boss Plus

Page 1: ...bricated tower scaffold system and should be used in conjunction with the appropriate corresponding BoSS scheme drawing EN1004 mobile access tower user guide and product datasheet BoSS IS A REGISTERED...

Page 2: ...14 Issue A FILE S140105 Drawn 29 01 2015 Page 2 OF 14 Issue A LINKED PREFABRICATED TOWER SCAFFOLD LADDERSPAN 3T BoSS IS A REGISTERED TRADEMARK OF YOUNGMAN GROUP LTD YOUNGMAN GROUP LTD 29 01 2015 FOR U...

Page 3: ...y Rated for External or Internal Use i e exposed to wind or not Maximum wind load Maximum foot load Tie loads where applicable Before each use Check that each prefabricated tower scaffold is complete...

Page 4: ...oved DURING Mobile tower structures shall be moved with the upmost caution Any stabilisers fitted must remain in position and raised no more than 25mm from the ground Prefabricated tower structures mu...

Page 5: ...the tower away from the structure at the point of access There must be no gap between the platform of the prefabricated scaffold tower and the place being accessed through which a person tools or mate...

Page 6: ...uipment are on site undamaged and that they are functioning correctly particularly the brace claw locking mechanism Damaged or incorrect components shall not be used Component weights can be found on...

Page 7: ...platfrom height tower starting with a 2 rung frame FILE S140105 Drawn 29 01 2015 Page 7 OF 14 Issue A LINKED PREFABRICATED TOWER SCAFFOLD LADDERSPAN 3T FILE S140105 Drawn 29 01 2015 Page 7 OF 14 Issu...

Page 8: ...opriate corresponding scheme drawing FILE S140105 Drawn 29 01 2015 Page 8 OF 14 Issue A LINKED PREFABRICATED TOWER SCAFFOLD LADDERSPAN 3T FILE S140105 Drawn 29 01 2015 Page 8 OF 14 Issue A BoSS IS A R...

Page 9: ...s open inwards as indicated with arrows Ensure all interlock clips are engaged 4 Fit Diagonal Braces between 13th and 15th rungs as shown FILE S140105 Drawn 29 01 2015 Page 9 OF 14 Issue A LINKED PREF...

Page 10: ...of the frames Ensure all wind locks are engaged FILE S140105 Drawn 29 01 2015 Page 10 OF 14 Issue A LINKED PREFABRICATED TOWER SCAFFOLD LADDERSPAN 3T FILE S140105 Drawn 29 01 2015 Page 10 OF 14 Issue...

Page 11: ...guardrailed 8 Fit Horizontal Braces to link the towers as shown FILE S140105 Drawn 29 01 2015 Page 11 OF 14 Issue A FILE S140105 Drawn 29 01 2015 Page 11 OF 14 Issue A BoSS IS A REGISTERED TRADEMARK...

Page 12: ...BoSS Infinity Multipurpose frames Move Stabilisers so that they are parallel to frames The build is now complete To dismantle the tower Simply follow the assembly steps in reverse ensuring that the 3T...

Page 13: ...forms located and wind locks engaged Interlock clips engaged Toe boards located Check guardrails are fitted correctly positively locked Tower use information and handover certificate in place FILE S14...

Page 14: ......

Reviews: