PRECAUTIONS DURING BRAZING SERVICE VALVE

Precautions should be taken to prevent heat damage to service valve
by wrapping a wet rag around it as shown in Figure 4. Also, protect all
painted surfaces, insulation, and plastic base during brazing. After braz-
ing, cool joint with wet rag.

Valve can be opened by removing the plunger cap and fully inserting a
hex wrench into the stem and backing out counter-clockwise until valve
stem just touches the chamfered retaining wall.

Connect the refrigerant lines using the following procedure:

1.

Remove the cap and Schrader core from both the liquid and vapor
service valve service ports at the outdoor unit. Connect low pres-
sure nitrogen to the liquid line service port.

2.

Braze the liquid line to the liquid valve at the outdoor unit. Be sure
to wrap the valve body with a wet rag. Allow the nitrogen to con-
tinue flowing.

3.

Carefully remove the plugs from the evaporator liquid and vapor
connections at the indoor coil.

4.

Braze the liquid line to the evaporator liquid connection. Nitrogen
should be flowing through the evaporator coil.

5.

Slide the grommet away from the vapor connection at the indoor
coil. Braze the vapor line to the evaporator vapor connection. After
the connection has cooled, slide the grommet back into original
position.

6.

Protect the vapor valve with a wet rag and braze the vapor line
connection to the outdoor unit. The nitrogen flow should be exiting
the system from the vapor service port connection. After this con-
nection has cooled, remove the nitrogen source from the liquid fit-
ting service port.

7.

Replace the Schrader core in the liquid and vapor valves.

8.

Go to “SECTION IV” for TXV installation.

9.

Leak test all refrigerant piping connections including the service
port flare caps to be sure they are leak tight. DO NOT OVER-
TIGHTEN (between 40 and 60 inch - lbs. maximum).

NOTE: 

Line set and indoor coil can be pressurized to 250 psig with dry

nitrogen and leak tested with a bubble type leak detector. Then
release the nitrogen charge.

NOTE: 

Do not use the system refrigerant in the outdoor unit to purge or

leak test.

10. Evacuate the vapor line, evaporator and the liquid line, to 500

microns or less.

11.

Replace cap on service ports. Do not remove the flare caps from
the service ports except when necessary for servicing the system.

12. Release the refrigerant charge into the system. Open both the liq-

uid and vapor valves by removing the plunger cap and with an
allen wrench back out counter-clockwise until valve stem just
touches the chamfered retaining wall. See Page 4 "PRECAU-
TIONS DURING BRAZING SERVICE VALVE".

13. Replace plunger cap finger tight, then tighten an additional 1/12

turn (1/2 hex flat). Cap must be replaced to prevent leaks.

See "System Charge” section for checking and recording system
charge.

SECTION IV: INSTALLATIONS REQUIRING 

TXV

For installations requiring a TXV, the following are the basic steps for
installation. For detailed instructions, refer to the Installation Instructions
accompanying the TXV kit.

Install TXV kit as follows:

1.

First, relieve the holding charge by depressing the Schrader valve
located in the end of the liquid line.

2.

After holding charge is completely discharged, loosen and remove
the liquid line fitting from the orifice distributor assembly. Note that
the fitting has 

right

 

hand

 

threads

.

3.

Remove the orifice from the distributor body using a small diame-
ter wire or paper clip. Orifice is not used when the TXV assembly
is installed.

4.

After orifice is removed, install the thermal expansion valve to the
orifice distributor assembly with supplied fittings. Hand tighten and
turn an additional 1/8 turn to seal. Do not overtighten fittings.

5.

Reinstall the liquid line to the top of the thermal expansion valve.
Hand modify the liquid line to align with casing opening.

6.

Install the TXV equalizer line into the vapor line as follows:

a.

Select a location on the vapor line for insertion of the equal-
izer line which will not interfere with TXV bulb placement.

b.

Use an awl to punch through the suction tube and insert the
awl to a depth to achieve a 1/8” diameter hole.

 Dry nitrogen should always be supplied through the tubing while it
is being brazed, because the temperature required is high enough
to cause oxidation of the copper unless an inert atmosphere is pro-
vided. The flow of dry nitrogen should continue until the joint has
cooled. Always use a pressure regulator and safety valve to insure
that only low pressure dry nitrogen is introduced into the tubing.
Only a small flow is necessary to displace air and prevent oxidation.

This is not a backseating valve. The service access port has a
valve core. Opening or closing valve does not close service access
port.
 If the valve stem is backed out past the chamfered retaining wall,
the O-ring can be damaged causing leakage or system pressure
could force the valve stem out of the valve body possibly causing
personal injury.

 FIGURE 4:  

Heat Protection

The evaporator is pressurized.

 Do not connect manifold gauges unless trouble is suspected.
Approximately 3/4 ounce of refrigerant will be lost each time a stan-
dard manifold gauge is connected.

Never attempt to repair any brazed connections while the system is
under pressure. Personal injury could result.

Summary of Contents for 12 SEER

Page 1: ...ular attention to the signal words DANGER WARNING or CAUTION DANGER indicates an imminently hazardous situation which if not avoided will result in death or serious injury WARNING indicates a potentia...

Page 2: ...ormed in order to insure proper sys tem operation and performance 1 Change out the indoor coil if required to an approved R 22 coil condensing unit combination with the appropriate metering device 2 I...

Page 3: ...periods of shutdown 6 Pack fiberglass insulation and a sealing material such as perma gum around refrigerant lines where they penetrate a wall to reduce vibration and to retain some flexibility 7 See...

Page 4: ...just touches the chamfered retaining wall See Page 4 PRECAU TIONS DURING BRAZING SERVICE VALVE 13 Replace plunger cap finger tight then tighten an additional 1 12 turn 1 2 hex flat Cap must be replace...

Page 5: ...n the inside surface of the unit service access panel 3 Replace the corner cover and service access panel that were removed in Steps 2 and 4 of the Field Connections Power Wiring section 4 All field w...

Page 6: ...MUST BE REMOVED 2 Y1 Y2 X L AND HUM LOCATED ON CFM SELECTION BOARD THERMOSTAT FIGURE 7 Typical Furnace Thermostat Wiring 1 VARIABLE SPEED FURNACE C Y R W HUMIDISTAT CONTACTS OPEN ON HUMIDITY RISE HUMI...

Page 7: ...s avail able add refrigerant accordingly Check flare caps on service ports to be sure they are leak tight DO NOT OVERTIGHTEN between 40 and 60 inch lbs maximum Superheat Charging Method NOTE Use this...

Page 8: ...When applicable instruct the owner that the compressor is equipped with a crankcase heater to prevent the migration of refrigerant to the compressor during the OFF cycle The heater is energized only w...

Reviews: