2. Installation, Piping, and Wiring
57
TI 11B08A01-01E
3
6
2
17
13
4
18
12
15
14
9
7
10
8
11
1
16
5
Figure 2.2
Accessory kit
Note: The picture is for illustrative purposes only. It is not be an exact representation of each part in the
dimension ratio to the actual one or the number of pieces contained in a kit.
Table 2.2
Item
Parts number
Quantity
Remark
Coil over wrench for LSV
L9827EA
1
Seal kit for LSV
K9402VG
number of LSV Rulon
Seal kit for LSV
K9402VH
number of LSV
Teflon
Ferrule
J9218VU
1 set
For capillary column
Ferrule
J9218VT
1 set
For megabore column
Cutter
J9218VV
1
For megabore or capillary column
User’s manual (CD)
—
1
IM 11B08A01-51E
Operation data
—
1
GCUD (CD)
K9809AA
1
For user programming option
Manual
K9809AN
1
For GCUD
(5) Installation
Use anchor bolts to secure the self-standing type analyzer on the floor. After the installation,
remove the fixture brackets.
Use nuts and bolts to secure the wall-mounting type analyzer on the wall. The wall construction
has to be designed to withstand four times the analyzer’s own weight.
For the hole for installation, refer to “1.2 External Dimensions.”
2.1.2
Installing Auxiliary Hardware
(1) Cylinders
The following conditions must be met:
(a) Located near the analyzer or the external sampling system.
(b) Not subject to rainfall or direct sunlight
(c) Ambient temperature: 0 to 40°C
(d) The place should be well-ventilated so that leaking gases, if any, do not accumulate.
Comply with regulations for high-pressure gases.
Sep. 07, 2017-00