YCW 750 OGP Curtain Wall System
Page-32
04-4031-15 | E
ff
ective Date: March 26, 2021
Sealant
Door Jamb
Subframe
Bed of
Sealant
YCW 750 OG
Door Jamb
FRAME INSTALLATION
STEP 17
INSTALL DOOR SUBFRAMES
Refer to the
Entrances Installation Manual
for assem-
bly of the door subframes. These subframes are typically
glazed into the curtain wall framing at the jambs, and set
directly upon the sill substrate without any shims. The
subframe members are determined by the approved
shop drawings.
-Clean all sealant contact surfaces as recommended
by the sealant manufacturer.
-Install the jamb subframe onto the mullion with
fasteners according to the approved shop
drawings and/or P.E. calculations, setting
the subframe jambs in beds of sealant as
shown in
Detail 35
.
-Apply and tool sealant to the bottom
of the jamb subframe as shown
in
Detail 36
.
Detail 35
Detail 36