![YASKAWA JVOP-182 Installation Manual Download Page 18](http://html1.mh-extra.com/html/yaskawa/jvop-182/jvop-182_installation-manual_3217106018.webp)
5 Installation Procedure
YASKAWA ELECTRIC
TOBP C730600 35B YASKAWA AC Drive Option LED Operator Installation Manual
19
■
Internal/Flush-mount Installation
The internal flush-mount installation method requires an installation support that is
purchased separately.
Refer to Item Names and Part Numbers (Sold Separately) on
for information regarding the installation support and mounting hardware.
illustrates how to attach the Installation Support A.
1.
Cut an opening in the enclosure panel for the LED Operator Option according to
.
2.
Mount the LED Operator Option to the installation support (sold separately).
3.
Mount the installation support and LED Operator Option to the enclosure panel.
Figure 8
Figure 8 Internal/Flush Mount Installation
Note:
For environments with a significant amount of dust or other airborne debris, use a gasket
between the enclosure panel and the LED Operator Option.
Figure 9
Figure 9 Panel Cut-out Dimensions (Internal/Flush-mount Installation)
Enclosure panel
Unit: mm (in)
LED Operator
Installation Support A
M4 × 10 (0.39)
Phillips truss head screw × 4
(for panel widths between
1 (0.04) and 1.6 (0.06))
M3
×
6 (0.24)
Phillips recessed
pan head machine screw × 2
120 (4.72)
Unit : mm (in)
45 (1.77)
89
+0.5 0
35
)
(
+0.02 0
59
+0.5
0
2.32
)
(
+0.02
0