ENGINE OPERATION
48
2V Operation Manual
CAUTION
Make sure the engine is installed on a
level surface. If a continuously running
engine is installed at an angle greater
than 25° (in any direction) or if an engine
runs for short periods of time (less than
three minutes) at an angle greater than
30° (in any direction) engine oil may
enter the combustion chamber causing
excessive engine speed and generating
white smoke. This may cause serious
engine damage.
0000010en2V
CAUTION
New Engine Break In:
• On the initial engine start-up, allow the
engine to idle for approximately 15
minutes while you check for proper
engine oil pressure, diesel fuel leaks,
engine oil leaks, coolant leaks, and for
proper operation of the indicators
and / or gauges.
• During the first hour of operation, vary
the engine speed and the load on the
engine. Short periods of maximum
engine speed and load are desirable.
Avoid prolonged operation at
minimum or maximum engine speeds
and loads for the next four to five
hours.
• During the break-in period, carefully
observe the engine oil pressure and
engine temperature.
• During the break-in period, check the
engine oil and coolant levels
frequently.
0000011en
CAUTION
NEVER hold the key in the START
position for longer than 15 seconds or
the starter motor will overheat.
0000007en
CAUTION
Observe the following environmental
operating conditions to maintain engine
performance and avoid premature
engine wear:
• Avoid operating in extremely dusty
conditions.
• Avoid operating in the presence of
chemical gases or fumes.
• Avoid operating in a corrosive
atmosphere such as salt water spray.
• NEVER install the engine in a
floodplain unless proper precautions
are taken to avoid being subject to a
flood.
• NEVER expose the engine to the rain.
0000003en
Summary of Contents for 0A2V000-U0000
Page 1: ...2V series OPERATION MANUAL 2V Operation Manual P N 0A2V000 U0000 INDUSTRIAL ENGINES 2V750 V ...
Page 12: ...YANMAR WARRANTIES xii 2V Operation Manual This Page Intentionally Left Blank ...
Page 16: ...TABLE OF CONTENTS xvi 2V Operation Manual This Page Intentionally Left Blank ...
Page 42: ...PRODUCT OVERVIEW 26 2V Operation Manual This Page Intentionally Left Blank ...
Page 100: ...PERIODIC MAINTENANCE 84 2V Operation Manual This Page Intentionally Left Blank ...
Page 108: ...LONG TERM STORAGE 92 2V Operation Manual This Page Intentionally Left Blank ...
Page 112: ...SPECIFICATIONS 96 2V Operation Manual This Page Intentionally Left Blank ...