When the water level in the boiler drops below the
middle probe, the circuit is broken which will 
a c t i vate the pump relay, turning the pump on. W h e n
the water level rises above the shortest probe, the
circuit is made and the pump relay is deactiva t e d ,
t u rning the pump off.

When the water level in the boiler drops below the
longest probe, the circuit is broken which will 
d e a c t i vate the bu rner relay, turning the bu rner off.
When the water level is restored to the middle
p r o b e, the bu rner relay will be activated (bu rner on)
for auto reset controls only.

SWITCH SETTINGS:

Chamber

STEP 1 - Installation

TOOLS NEEDED:

One (1) pipe wrench, one (1) flathead screwdriver and/or 11/32" nut driver,
one (1) metal-cutting saw, one (1) 9/16" socket or wrench and pipe sealing compound.

If the control will be the primary low water fuel
cut-off,

size the steam (top) and water (bottom)

equalizing pipe lengths to the chamber so that the

cut-off level mark is 1

1

/

2

" (38mm) below the 

boiler’s normal water level, but not lower than
the lowest safe permissible water level, as
determined by the boiler manufacturer.

OR

If the control will be the secondary low water
fuel cut-off,

s i ze the steam (top) and water (bottom)

equalizing pipe lengths to the chamber so that the

cut-off level mark is at or abov e the lowest safe
p e r m i s s i bl e water level, as determined by the
boiler manufacturer.

• Mount 

C o n t rol Box

in a suitable location near

the boiler’s main electrical panel.

• Install electrical conduit between electrical

enclosure of the 

P robe Chamber

and

C o n t rol Box .

• Pull four (4) wires through conduit.

Boiler sight glass must be visible from location of
Control Box and must be within 25 feet of Control
Box.

NOTE

R e fer to and fo l l ow local codes and standard s
when selecting conduit and electrical fittings.
Wires from Electrical Enclosure of the Pro b e
Chamber to Control Box must be in their own 
c o n d u i t . If they are run in conduit with other wires,
there may be interference that can affect the 
performance of the control.

NOTE

Wire must be 18 AWG stranded with glass braided
silicone jacket (UL 3071) suitable for high temper-
ature (200˚C) service.

NOTE

SPECIFICATIONS (cont.)

Summary of Contents for McDonnell & Miller 1575 Series

Page 1: ...secondary redundant Low Water cut off controls be installed on all steam boilers with heat input greater than 400 000 BTU hour or operating above 15 psi of steam pressure At least two controls should...

Page 2: ...ctivated turning the pump on after water drops below the middle probe If the water level is not restored to the top probe within 3 m i nutes the pump relay will be deactivated shutting off the pump Af...

Page 3: ...System Water Temperature 406 F 208 C Maximum System Water Pressure 250 psi 17 6 kg cm2 Maximum System Steam Pressure 250 psi 17 6 kg cm2 All probes in the Series 1575 units are sent from the factory p...

Page 4: ...l water level but not lower than the lowest safe permissible water level as determined by the boiler manufacturer OR If the control will be the secondary low water fuel cut off size the steam top and...

Page 5: ......

Page 6: ...over Removal and Installation Procedure a To remove cover use a flathead screwdriver to loosen screws and remove the cover K b To reconnect cover slide over brackets and tighten screws using a flathea...

Page 7: ...p Control Connect wire a from power supply to terminal H Connect wire b from neutral supply to terminal N Connect wire c from valve control circuit to terminal PNO Connect wire d from valve control ci...

Page 8: ...PCB is too hot and the unit has shut down The unit will automatically restart when the PCB has cooled sufficiently When using the TEST button the green light will flash once per second during the time...

Page 9: ...nit is factory set at 0 seconds To adjust turn the adjusting screw clockwise using a small flatblade screwdriver to the delay time desired Followthe bl owdown procedure found on page 11 to verify oper...

Page 10: ...pect probes The wiring connections for the pump may not be connected properly Check wiring at terminals Burner does not turn off when water level is below longest probe The probes may be fouled with d...

Page 11: ...ld be opened slowly The piping needs to be wa rmed up and stagant water in the drain piping needs to be pushed out Suddenly opening a blow down valve causes steam to condense which may create water ha...

Page 12: ...poses Seller warrants the goods purchased hereunder with the exception of membranes seals gaskets elastomer materials coatings and other wear parts or consumables all of which are not warranted except...

Reviews: