Planning
2–6
152315 Rev C
Layout Options
The PV100S is shipped as two separate assemblies and can be arranged as shown
in Figure 2-1 or Figure 2-2.
The PV100S can be arranged in a number of different system layout options to fit
specific site requirements. The AC interface/transformer assembly may be
co-located adjacent to the left side of (or behind) the Main Inverter Enclosure up
to, and not exceeding, 15 feet away.
Given the flexibility to co-locate the AC interface/transformer assembly to fit a
desired system layout, the interconnect AC power conductors and conduit
between the Main Inverter Enclosure and the AC interface/transformer assembly
are to be supplied by the installer. See Figure 2-1 and Figure 2-2, depicting two
options for locating the AC interface/transformer assembly adjacent to the main
inverter.
Figure 2-1
PV100S Layout Option A
Transformer
Enclosure
Inverter
Enclosure
DC Interface
Enclosure
AC
Interface
Enclosure
Communications
Enclosure
6" Minimum Clearance
Minimum
Clearance*
(15' Max. Distance
from Inverter)
12"
Conduit
36"
Minimum
Clearance
36"
Minimum
Clearance
12' (3.6 m)
6'
(1.8 m)
36"
Minimum
Clearance
BASE: Concrete Floor or Pad
Approximately 12 ft by 6 ft
(3.6 m x 1.8 m)
Minimum
Clearance
12"
Minimum
Clearance
12"
36"
Minimum
Clearance
Minimum Dimension of Base:
Approximately 12 ft. by 6 ft. (3.6 m x 1.8 m)
Summary of Contents for PV100S-480
Page 2: ......
Page 3: ...PV100S 100 kW Grid Tied Photovoltaic Inverter Planning and Installation Manual...
Page 8: ...vi...
Page 14: ...xii...
Page 18: ...xvi...
Page 77: ...A Schematics Appendix A contains useful schematics to aid with installation...
Page 78: ...Schematics A 2 152315 Rev C This page intentionally left blank...
Page 79: ...Appendix A Schematics 152315 Rev C A 3 Figure A 1 Electrical Diagram sample...
Page 86: ...Schematics Appendix A A 10 152315 Rev C This page was intentionally left blank...
Page 89: ......