3.5.1.2 AC Connection
Prerequisites:
•
All grid parameters must be fulfilled (Section 11.2.1).
Figure 12: AC connection
Pos. Description
1
AC circuit breaker
2
AC connection
3
PE conductor connection
4
Neutral conductor connection
Procedure:
1.
Observe
the sequence (Figure 12).
2.
Connect
the cables for L1, L2, L3 to the corresponding terminals on the AC
circuit breaker.
3.
Tighten
the screws with a torque of
7-8 Nm
.
NOTICE: The cable lugs must be suitable for a M8 screw with a maximum width of
18 mm.
4.
Connect
the neutral conductor to the terminal (-X19).
5.
Tighten
the screws with a torque of
15-20 Nm
.
NOTICE: The terminal is suitable for conductor cross-section up to 240 mm
2
.
6.
Fix
the cables with cable clamps.