Requirements for the installation site:
•
Foundation and formwork must be built according to applicable local
regulations and standards.
•
Ensure that there is sufficient room for installation, mounting, operation and
repair.
•
Required ambient conditions must be fulfilled (Table 11).
•
Ensure that the minimum required distances for escape routes must be
followed according to applicable local regulations and standards.
•
The product must be positioned on a foundation that ensures sufficient air
circulation.
•
The moved cooling air volume can be seen in Table 11.
•
The product must be properly positioned on the foundation.
Figure 7 shows the mounting points of the product. All dimensions are given in
millimetres.
Figure 7: Cable entry area (bottom view)
Pos. Description
1
Cable entry area (without sliding ground plate)