28
PRE-COMMISIONING CHECKS
PRE-COMMISIONING CHECKS
8-716-109-711a (04.05)
CAUTION: ISOLATE THE MAINS SUPPLIES
BEFORE STARTING ANY WORK AND
OBSERVE ALL RELEVANT SAFETY
PRECAUTIONS.
1 Check that the service and water pipes are
connected to the correct valves
Check that all unused sockets are plugged
2 Check that the oil supply is 28 sec Kerosene
and that the pipework is connected correctly to
the oil pump
Turn on the main oil supply valve at the tank
and check the oil supply pipework, connections
and rectify any leaks
3 Check the flue is correctly fitted and the
connections are secure
4 Check the condensate pipework is correctly
fitted and connected
Check the condensate trap is filled with water.
IMPORTANT: If the boiler is not to be
commissioned immediately then:
after successfully completing all of the
checks and any rectification work, close the
water valves, shut off the oil supply and
electrically isolate the boiler.