INSPECTION
6 720 648 726 (2011/07)
63
12.12 INSPECTION LOG BOOK
B
Enter your signature and the date after completing the inspection activities.
Inspection activities
Date: ________
Date: ________
Date: ________
1.
Checking the general condition of
the heating system.
2.
Carrying out a visual inspection and
function test of the heating system.
3.
Checking the gas and water-bearing
system components for:
•
Operational tightness
•
Visible corrosion
•
Signs of wear.
page 54.
Section 12.3,
page 61.
4.
Measuring the ionisation current.
page 55.
___________
μ
A
___________
μ
A
___________
μ
A
5.
Measuring the gas supply pressure
(working pressure).
page 51.
________ mbar
________ mbar
________ mbar
6.
Checking the gas/air-ratio.
page 51.
_________ Pa
_________ Pa
_________ Pa
7.
Carrying out a tightness check of the
gas circuit in operating conditions.
page 54.
8.
Measuring the carbon monoxide
content (CO), air free.
page 55.
_________ ppm
_________ ppm
_________ ppm
9.
Checking the system pressure.
•
Pre-pressure of expansion vessel
(also see installation instructions
for expansion vessel)
•
Filling pressure.
Section 10.1,
page 47.
_________ bar
_________ bar
_________ bar
_________ bar
_________ bar
_________ bar
10.
Checking the operation and safety of
the air intake and flue gas pipe.
page 51.
11.
Checking the boiler settings of the
control device (in accordance with
requirements).
See the
documents for
the control
device.
12.
Final check of the inspection
activities, documenting the
measurement and test results.
13.
Confirming proper inspection.
Company
stamp/
signature/
date
Company
stamp/
signature/
date
Company
stamp/
signature/
date
Table 20