10  PUTTING INTO OPERATION 

The instrument comes into operation as soon as the root valves 

are opened and then, afterwards, the service valve attached to 

the inst (H) inlet pipe is opened, the by-pass valve 

closed and the service valve attached to the instrument – (L) inlet 

pipe is opened. Any possible drainage of the connection tubing 

can be carried out by opening the drains positioned on valves. 
Do not dispose of the process fluid into the environment, if this 

can cause pollution or damage to people 

11 VISUAL 

INSPECTION 

Periodically check the external condition of the enclosure. There 

should be no trace of leakage of process fluid outside the 

instrument.  

In case of intrinsic safety instruments, inspections of the electrical 

installation are to be carried out also according to customer 

procedures and at least in accordance with IEC-60079-17. 
The intrinsic safety instruments installed in explosive 

atmospheres for the combustible dust presence, must be 

periodically cleaned up externally in order to avoid dust 

accumulating. 

12 FUNCTIONAL 

VERIFICATION 

This will be carried out according to the Customer’s control 

procedures and because of their particular operating principle, 

have to be functional inspected every year as minimum if used 

as an alarm of max pressure  
The instruments can be verified on the plant if installed as 

illustrated in Fig. 14. 

To avoid any risk it is recommended check the set point on site 

without open the cover, without dismount the cable gland and  

without unplugging the power cable. 
The intrinsic safety instruments may be checked on site only if 

the apparatus used are suitable for explosive atmosphere.  
If this is not the case it is necessary remove the instrument from 

the plant, and carry out the verification in a testing room. 

If the verification of the set point is performed unplugging the 

power cable from the terminal block it is recommended de-

energize the instrument to avoid any electrical hazard. 

Verification consists in 

check the calibration value

 and possibly 

regulating the adjustment bush (see §5).  

13 STOPPING 

AND 

DISMOUNTING 

Before proceeding with these operations 

ensure 

that the plant or 

machines have been put into the 

conditions

 foreseen to allow 

these operations. 

With reference to Figures 14

 

Remove the power supply (signal) from the electrical line. Close 

the root valves (6) and open the by-pass valve. Open the drains 

on the root valves slowly. 
Do not dispose of the process fluid into the environment, if this 

can cause pollution or damage to people. 
Unscrew the three-piece joint (1). 

Unscrew the cable gland (9). 

Remove the cover of the instrument and disconnect the electrical 

cables from the terminal block and earth screws. 

Remove the screws fixing the case to the panel and remove the 

instrument, taking care to slide the electrical conductors out from 

the case. 

Mount instrument cover. Insulate and protect cables around, if 

any. Temporarily plug pipes not connected to the instrument. 
In case of intrinsic safety instruments it is recommended to follow 

- at least – the standard IEC-60079-17 for the withdrawal from 

service of electrical apparatus.  

14 DISPOSAL 

The instruments are mainly made of stainless steel and 

aluminium and therefore, once the electrical parts have been 

dismounted and the parts coming into contact with fluids which 

could be harmful to people or the environment have been 

properly dealt with, they can be scrapped. 
 

15 TROUBLESHOOTING 

IMPORTANT NOTE

: operations involving replacement of essential components must be carried out at our workshop this is to guarantee 

the user the total and correct restoration of the product original characteristics. 
 

MALFUNCTION PROBABLE 

CAUSE 

REMEDY 

Set point shift 

 

 

 Permanent deformation of the sensitive element 

due to fatigue or non-tolerated over-ranges 

 Variation of the elastic features of the sensitive 

element due to its chemical corrosion. 

  Recalibrate or replace the sensitive element. 

 

 Recalibrate or replace the sensitive element with 

another made of a suitable material. 

 

Slow response 

  Clogged or obstructed connection line.  

  Root or service valve partially closed. 

  Check and clean line. 

 Open valve. 

No actuation or 

undue actuation 

  Root or service valve closed. 

  By-pass valve open. 

 Microswitch contacts damaged. 

  Loosened electrical joints. 

  Interrupted or short-circuited electrical line.

 

 Open the valve. 

  Close the valve. 

 Replace the microswitch. 

  Check all electrical joints. 

  Check the conditions of the electrical line. 

Undue actuation 

 

Accidental shocks or excessive mechanical 

vibrations.

 

 Modify the mounting.

 

 

Fig.10 – DW03 wall mounting 