Weil-McLain SGO Series Maintenance And Service Manual Download Page 11

11

Detailed Service Procedures

Controls requiring annual service:

FLOAT

-TYPE LOW  WATER CUTOFF:

Follow instructions to blowdown cutoff on page 4. 
Also refer to instructions from cutoff manufac-
turer in envelope assembly provided with boiler.

PROBE

-TYPE LOW  WATER CUTOFF:

Cutoff must be removed and inspected and 
cleaned annually. Refer to cutoff manufacturer's 
instructions in envelope assembly provided with 
boiler.

STEAM RELIEF VALVE:
Check operation of steam relief valve. Follow  
instructions on label fastened to relief valve.

    Scald 

potential. 

Do 

not 

check 

operation of relief valve unless discharge piping 
has been installed according to Boiler Manual. 
If piping is not in place, a qualified service 
technician must properly install piping. 

GAUGE GLASS:
To clean glass:
1.  Close lower gauge glass cock and carefully  
 

open petcock below glass to blow water and  

 

sediment out of glass by steam pressure.

2.  Slowly open lower gauge glass cock and allow  
 

a small amount of water to flush out through  

 

the open petcock.

3.  Close petcock and fully open lower gauge cock.  
 

The water level should immediately rise to its  

 proper 

level.

4.  If gauge glass breaks, close off both gauge  
 

cocks and loosen glass retaining nuts to  

 

remove gauge glass. Do not use thin glass 

 

tubing as a replacement.

General description of control operation:

LOW  WATER CUTOFF:

Shuts down boiler if there is a low water condi-
tion. 

STEAM RELIEF VALVE:

Provides discharge if boiler pressure exceeds 15 
psig. 

PRESSURE LIMIT CONTROL:

If high steam pressure occurs, control shuts 
down burners until pressure drops. Limit should 
be set higher than design pressure of system. Op-
erating control can be set at 5 psig and 
adjusted to comfort level. Normal operation is 
usually less than 5 psig. At certain times the 
system may operate under vacuum conditions.

GAUGE GLASS:

Indicates boiler water level. Cold fill water level 
should correspond to line stamped on boiler 
jacket. When boiler operates, water level will fluc-
tuate.

PRESSURE GAUGE:

Provides reading of boiler pressure.  Maximum 
boiler pressure is 15 psig.

TANKLESS WATER HEATER:

Weil-McLain tankless heater ratings are based on 
200

0

F boiler water temperature. To get rated out-

put, set tankless heater control to 200

0

F. Control 

can be adjusted to meet system hot water require-
ments. 

Part No. 550-141-830/1202

Summary of Contents for SGO Series

Page 1: ...or future reference leave this manual with other boiler instructions in the envelope provided with the boiler Maintenance and Service Guide Part No 550 141 830 1202 SGO Series 3 Oil Fired Steam Boiler...

Page 2: ...ine maintenance of boiler and system Pages 2 through 6 must be followed to assure proper operation of your boiler Page 7 lists common problems and possible corrections In addition it is your responsib...

Page 3: ...gasoline See burner manual for proper fuel oil Do not attempt to start burner when excess oil has accumulated in combustion chamber when unit is full of vapor or when combus tion chamber is very hot D...

Page 4: ...t type low water cutoff when used Refer to control manufacturer s instructions Scald potential Do not blow down low water cutoff unless blowdown piping has been installed according to Boiler Manual If...

Page 5: ...team ReliefValve on back of boiler SGO with oat type low water cutoff 1 If burner does not re check for Switch on boiler or additional shut off switches turned off Fuses or breaker switch tripped Ther...

Page 6: ...turned off Fuses or breaker switch tripped Thermostat set below room temperature Fuel valves turned off Not enough oil in tank to supply burner No water in gauge glass Start up SGO Boiler with Probe T...

Page 7: ...pair clean or replace air vents or traps Water disappearing from gauge glass and back into system through return piping Incorrect Hartford Loop piping Have qualified service technician pipe boiler exa...

Page 8: ...ds 2 Check for and remove any obstruction to combustion and ventilation air flow to boiler 3 Check breeching and chimney or vent for obstructions damage etc Repair or replace as necessary 4 Clean boil...

Page 9: ...Move to the bottom of the ueways and clean up between the sections to reach pins left uncleaned in step 5 Thoroughly clean ueways between all pins at all angles Start on top of boiler nish from the b...

Page 10: ...aps and air vents for proper opera tion 7 Process may need to be repeated after several weeks of operation L L L L Detailed Service Procedures To place in operation Follow information below to prevent...

Page 11: ...cock The water level should immediately rise to its proper level 4 If gauge glass breaks close off both gauge cocks and loosen glass retaining nuts to remove gauge glass Do not use thin glass tubing...

Page 12: ...Part No 550 141 830 1202...

Reviews: