Burner adjustments for “P” and “A” boilers:
Final burner adjustments must be
made using combustion test
equipment to assure proper operation. Do not fire
boiler without water or sections will overheat.
1. Refer to burner manual for start-up.
2. Allow boiler to heat to design condition.
3. Using combustion test equipment, adjust
burner for:
a. CO
2
between 11% and 12% and 0 smoke.
b. -0.01" to -0.02" W.C. draft in
combustion chamber.
To connect SGO boilers to indirect-fired
water heaters:
Install and wire per water heater manual provided
with water heater.
If boiler already has a tankless heater installed:
•
Remove tankless heater and install cover plate.
OR
•
Leave tankless heater installed. Drain coil and
remove piping. Do not plug holes in tankless
heater front plate.
27
Appendix
Summary of Contents for 550-141-829/1201
Page 9: ...Install Non Packaged Boiler CONTINUED ...
Page 11: ...Install Packaged and Non Packaged Boiler ...
Page 15: ...Connect Steam Piping CONTINUED ...
Page 16: ...Connect Steam Piping CONTINUED ...
Page 20: ...20 Connect Wiring CONTINUED ...
Page 22: ...22 Connect Wiring CONTINUED ...
Page 29: ...Parts Drawing ...
Page 31: ...Dimensions CONTINUED ...
Page 32: ......