2.1 Scope of Supply 

 

Check the delivered goods for damage. Damages caused by transport must be reported immediately to the dealer and the 

WEHA company. Also check if all parts are present. 

The scope of supply consists of: 

 

2 x perforated rails  

 

20 x iron tubes (RR); 16x iron tubes (Magnum / Bison / IRAXX) 

 

1 x operation manual 

 

2.2 Assembly instructions 

 

The support stand must be assembled. 

When unpacking, transporting and assembling, take care not to damage the galvanized metal parts with sharp-edged objects. 

The panel stand can be mounted without the use of special tools. 

In principle, the support stand is mounted as follows: 

 

Place the rails directly on the ground parallelly to each other. 

 

 

Insert the iron tubes into the holes. 

IT IS IMPERATIVE TO FOLLOW:  

 

The ground must be horizontal, level and firm. Make sure of this with a spirit level and a shaking the tubes. 

 

The rails must always run parallel, i.e. have the same distance to each other over the entire length of the support 

stand. 

 

Select the distance between the outer sides of the rails in such a way that it equals the width of the panels to be 

stored, in order to avoid the stand tipping over sideways. 

 

Distribute the tubes equally on both sides, i.e. 10 or 8 tubes per perforated rail. All tubes supplied must be inserted. 

 

Distribute the tubes in such a way that they are inserted in the same holes in both perforated rails, i.e. if they occupy 

holes 1, 4, 7 and 10 in rail 1, for example, they must also occupy holes 1, 4, 7 and 10 in rail 2. Never insert the tubes 

into the rails offset to each other. 

 

Make sure that the tubes are fully inserted into the holes. 

 

Always check that all tubes are in perfect working condition and that no deformations or cracks are visible. 

 

 

a, b = Distance of the rails to each other 

2 rails 3000mm each 