5
8. Shims
The Pronto!™ floor drain comes equipped with two plastic leveling shims. These
may be used when the finished drain assembly is slightly tilted.
Leveling Shims
On-Grade Slab Installation
It is recommended to use a bead of silicone around the last thread of the top
assembly.
Screw the top assemby down until the bottom of the frame is flush with the
concrete.
Use a bead of silicone around the perimeter of the strainer frame.
Gently turn the head clockwise until the top of the strainer sits flush with the finish
floor.
0-7/8" Adj.
After Pour
3 3/8"
(85)
Adjust After
Concrete Pour
• Continue tapping until a visible crack forms around the edge of the top assembly.
• The top should loosen and separate from the concrete by using the pliers to
grasp the edge tabs around the recessed screw holes and popping the top up.
(A straight edge screwdriver may also be used to pry the top up)
Do not use excessive force when tapping against the cover. Excessive
force may cause pliers to slip and cause damage to the concrete floor.