STEP 6

Opening Speed Flow Control Adjustment: The Opening speed 

flow control allows free flow into the cover and restricted flow out 

of the cover of the main valve. If recovery of the pressure is slow 

upon increased downstream demand, turn the adjustment screw 

OUT, counterclockwise, increasing the rate of opening. If recov-

ery of downstream pressure is too quick, as indicated in a rapid 

increase in pressure, possibly higher than the desired set-point, 

turn the adjustment screw IN, clockwise, decreasing the rate of 

opening (See Figure 3).

STEP 7

(If the main valve comes equipped with a closing speed control, 

otherwise ignore this step.)

Closing Speed Needle Valve Adjustment: The closing speed 

needle valve regulates fluid pressure into the main valve cover 

chamber, controlling the valve closing speed. If the downstream 

pressure fluctuates slightly above the desired set point, turn the 

adjustment screw OUT, counterclockwise, increasing the rate of 

closing.

Counterclockwise to INCREASE 

the rate of opening

Clockwise to DECREASE 

rate of opening

Figure 3 

Flow Control

4          IOM-A-ACV-910-17_610-17   2115 

EDP# 1917040 

© 2021 Watts

IOM-A-ACV-910-17_610-17   2115 

EDP# 1917040 

© 2021 Watts         5

Summary of Contents for Ames 910GD-17

Page 1: ...the Pressure Reducing Control 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to the in...

Page 2: ...inlet and outlet pressures A Position Indicator can be installed to provide visual indication of valve position and operation without disassembly 3 Install isolation valves upstream and downstream of...

Page 3: ...at the highest point of the valve assembly STEP 3 Pressure the line by opening the upstream isolation valve slowly Air is vented through the air bleed valve or loosened fitting Tighten the fitting wh...

Page 4: ...esired pressure setpoint by turning the adjustment screw IN clockwise to increase or OUT counterclockwise to decrease downstream pressure See Figure 2 Counterclockwise to DECREASE downstream pressure...

Page 5: ...he adjustment screw IN clockwise decreasing the rate of opening See Figure 3 STEP 7 If the main valve comes equipped with a closing speed control otherwise ignore this step Closing Speed Needle Valve...

Page 6: ...specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm...

Page 7: ...ly by partially opening from full closed position Improperly configured opening speed control if equipped Adjust opening speed control to verify functionality adjust as required Standard setting for o...

Page 8: ...move cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require...

Page 9: ...rush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are thread...

Page 10: ...ts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrit...

Page 11: ...el 9 Stem Washer ASTM A276 304 Stainless Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iro...

Page 12: ...resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances over which the Company has no cont...