8.12 RETURNING THE BOILER TO SERVICE AFTER SHUTDOWN
After a prolonged shutdown (one year or more), the following procedures must be followed:
Placing the Boiler Back in Service After A Prolonged Shutdown Instructions
1. Review installation requirements included in Section 2 of the
Benchmark 750-6000 with
Edge [i]: Install-Startup Manual
(OMM-0144, GF-217)
.
2. Inspect all piping and connections to the unit.
3. Inspect exhaust vent and air inlet duct work (if applicable).
4. Perform initial startup per Section 4 of this guide.
5. Perform the instructions in Section 5:
Safety Device Testing
, above, and all scheduled
procedures described Section 8:
Maintenance
.