115
|
217
Product Overview
Operation
Connecting the Manual Override—Optional
1
2
Use the illustration and instructions to connect the
optional manual-override switch and power relay.
1 To install the manual-override switch, do the
following:
•
Install the manual-override switch into the
operator panel.
•
Use the manual-override cable to connect it
to the PDM control box—the manual override
switch connection.
Note:
Use an M12 cable extensions if
necessary.
2 To install the manual override power relay, do
the following:
•
Use the mounting holes to install the relay to
the apparatus.
•
Connect the power input post to apparatus
power. Refer to:
.
•
Connect the power output post to DLA
breaker box. Refer to:
Connections—Overview" on page 93
•
Use the manual override relay cable and an
M12 cable extension to connect the relay to
the PDM control box—the override relay
connection.
I-2259 L-1222-9