Electrostatic charging (formation of
sparks or flame)
Under certain circumstances, electrostatic
charging can occur on the unit due to the ra-
te of flow of the coating material when
spraying. On discharging this can result in
the emergence of sparks or fire. It is therefo-
re necessary that the unit is always earthed through the
electrical installation. The connection must take place
through a correctly earthed two-pole-and-earth socket
outlet.
Using unit on construction sites
Connection to the mains only through a special feed
point, e.g. through an error protection installation
with INF
≤
30 mA.
Ventilation when spraying in rooms
Adequate ventilation must be guaranteed for the removal
of the solvent vapours.
Suction installations
These are to be set-up by the user of the unit according
to local regulations.
Earthing of the object
The object to be coated must be earthed.
Cleaning units with solvents
When cleaning the unit with solvents, the sol-
vent should never be sprayed or pumped
back into a container with a small opening
(bunghole). An explosive gas/air mixture can
be produced. The container must be earthed.
Cleaning the unit
Danger of short circuit through pene-
trating water!
Never spray down the unit with high-pres-
sure or high-pressure steam cleaners.
Work or repairs on the electrical
equipment
Only have this work carried out by a qualified electrician.
No liability will be taken for incorrect installation.
Working on electrical components
Remove the mains plug from the socket for all such
works.
Danger
Danger
Danger
HC 35 E • HC 45 E • HC 55 E
33
g
Setting-up on uneven surfaces
The front side of the unit must point downwards to pre-
vent sliding away.
Safety regulations
General view of application
2. General view of application
2.1
Application
Priming and final coating of large areas, sealing, impreg-
nation, construction sanitation, façade protection and
renovation, rust protection and building protection, roof
coating, roof sealing, concrete sanitation, as well as
heavy corrosion protection.
Examples of objects to be sprayed
Large-scale construction sites, underground construc-
tion, cooling towers, bridges, sewage treatment plants
and terraces.