5
Note
Observe all relevant accident prevention
regulations.
Only use the marked fixing points.
1. Lifting the boiler
Use lifting eyes
A
or lifting area
D
on the boiler support.
2. Moving the boiler
For this, fit steel rollers underneath
base rail
C
.
3.
Secure the pulling equipment to the
tie-down points
B
.
45°
45°
F1/2
90°
A
B
F1/2
C
F1/2
F1/2
D
D
Lifting eyes
A
:
7
80
Tie-down points
B
for IPB
120:
7
≤
60
Note
Boiler shown with an optional integral
economiser.
Handling the boiler
5607 279 GB