13
Required parts:
■
Adjusting screws
A
are supplied with the boiler.
!
Please note
Damage to the flue gas connection can result in
leaks.
Never lift or move the boiler by the flue outlet.
Note
The installation room must be equipped with a suitable
condensate drain (maximum 50 mm above floor level)
if the boiler is installed at ground level.
A
2.
1.
B
B
C
C
Fig. 7
Note
Use holes
B
and
C
in the boiler floors to attach lifting
tackle.
1.
Insert adjusting screws
A
into the base rails from
above.
2.
Level the boiler horizontally. Special foundations
are not required.
Note
We recommend installing the boiler on
adjustable
anti-vibration feet
(accessories).
Insert adjustable feet into the base rails from
below.
Siting and levelling the boiler
5833527