If required, all models are easily repairable.  The ball bearings can easily be changed by any maintenance mechanic 

by removing the two end covers and pressing out the damaged bearings from the turbine wheel. Remove both nuts, 

press the shaft out of the bearings and turbine.  Note: Use Andok C or Unirex N2 (by Exxon) or equal type of grease.  

When reassembling be sure the turbine wheel is put back so that the incoming air will hit the pocket of the tooth, not 

the back of the tooth.

When new, the turbine vibrator might be slow in starting due to:

A. 

The bearings being packed with grease.  Excess grease will be thrown out of the bearing after a short 

operating time.

B.

 

Temperature might be low causing the grease to be stiff.  After a short operating time the grease will warm 

and begin to loosen.

C.

 

Bearing seals are stiff when new or cold.  A brief run time will wear them in.

Sudden loss of vibration:

 

A. 

Loss of vibration could be caused by a cracked weld or a crack in the bin. Vibration will not travel through a 

crack.  Follow the instructions below on how to fix the problem.

Troubleshooting

The improper welding of bin stiffeners, to which the vibrator is attached, often results in fatigue cracks in the bin.  

This can be preventd by properly welding stiffeners to the bin side.  A stiffener should be stitch welded to the bin leav-

ing 3 to 4 inches between welds.  STOP WELDS 1 IN. FROM THE ENDS OF THE STIFFENER.  This will prevent 

fatigue cracks that occur due to crystalization of the material.  This crystalization is caused by the heat concentration 

that develops when the ends of the channel iron are welded.  To stop the cracks, drill a hole at the end of each crack 

and weld on a piece of angle iron as shown above.  When welding on the angle iron STOP WELDS 1 IN. FROM 

THE ENDS.

3  or  4  in.

c h a n n e l

Do not weld 1 in. from 

end of stiffener

Mounting plate

for vibrator

Stop welds at least 1 in. 

from ends

If cracks have developed, drill holes at the ends of the 

cracks and weld on angle iron as shown

13

PHONE ORDER: 1-800-633-0032          FAX: 1-401-539-2584

WWW.VIBCO.COM          [email protected]

The Vibrator Won’t Start!

1. Check for dirt in the airline OR inlet opening
2. Check for dirt or debris clogging the exhaust muffler
3. Double check the size of your air line - is it large enough to give you the correct cubic feet per minute (CFM) and 

correct air pressure (minimum required =  20 PSI)?
4.  Did you mount the air regulator far enough away from the quick acting valve for the right amount of air pressure 

to build up?

NOTE:

 Beraings may require a short “break-in” period to run at optimum VPM stated in the catalog 

Summary of Contents for BBS-100

Page 1: ...AZ 85254 Phone 800 633 0032 480 596 1809 Fax 480 596 1614 Canada 2215 Dunwin Drive Mississauga ONT L5L 1X1 Phone 800 465 9709 905 828 4191 Fax 905 828 5015 E mail vibrators vibco com Website www vibco...

Page 2: ...________ Date of Purchase ____________________ Safety Instructions 2 Mounting Instructions Checklist 3 Mounting Procedures 3 4 Mounting To Bin Walls Or Chutes 5 8 Vibrator Installation and Pneumatic H...

Page 3: ...ring range making it virtually silent Turbine vibrators average a whisper quiet 72 dB The BBS BVS MLT and MLTSS models should use a muffler to remove exhaust air hiss The VS model has a built in muffl...

Page 4: ...the vibrator See Table Warranty is void if vibrator is not properly installed During installation follow and check off the following steps and your vibrator should provide you with years of trouble f...

Page 5: ...ge opening to the top of the sloped portion of the bin Stitch weld channel iron in place then weld intermittent welds 3 to 6 long with 3 between them along the entire length of the channel Stop weld a...

Page 6: ...ular Bin One Vibrator For A Double Bin Bin With Stiffeners Angle Iron Stiffeners Instead of Channel Iron Thin Skinned Bin Corner Mount 5 1 2 L 1 3 L L Two Vibrators On A Single Bin PHONE ORDER 1 800 6...

Page 7: ...in front and the front vibrator has turned off For more details consult Vibco Feeds from back Vibrator should be placed 1 3 from the back If 2 vibrators are used place 2nd one directly opposite 1 3 fr...

Page 8: ...bearing failure Also ask for high temperature grease in vibrator bearing Consult VIBCO for vibrator size Use steel plate on inside and bolt to outside mounting channel Mount steel plate on inside of...

Page 9: ...needed one should be placed 18 24 from the discharge The other approximately in the middle Since chutes are very sensitive to vibration provision should be made to move the lower vibrator 6 inches in...

Page 10: ...that it is secured tightly Retighten the bolts after the first 10 to 15 minutes of operation and check them periodically to maintain proper tightness figures 1 and 2 VIBRATOR INSTALLATION Damage to th...

Page 11: ...e suggested for automatic operations Automatic Timed Cylcling is programmed with the timer usually directly connectd to the bin or hopper gate switch When the gate is opened the timed cycling system i...

Page 12: ...BCO Max air pressure for BVS 60 VS BBS and FBS 100 should be 60 psi Figure 3 Maximum Temperature The operating temperature of the vibrator should not exceed 200o F 93o C High temperature units are ava...

Page 13: ...the Unit The life of the vibrator will be determined by the length of operation and the cleanliness of the air supply Guaranteed Success of the Application The vibrator can only furnish material to th...

Page 14: ...he bin This can be preventd by properly welding stiffeners to the bin side A stiffener should be stitch welded to the bin leav ing 3 to 4 inches between welds STOP WELDS 1 IN FROM THE ENDS OF THE STIF...

Page 15: ...BBS and FBS Technical Data 14 PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM L I D G A C H E W...

Page 16: ...VS Technical Data 15 PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM...

Page 17: ...BVS Technical Data 16 PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM...

Page 18: ...MHISS 130 2 3 4 70 1 4 6 3 1 2 89 1 7 8 48 2 3 8 64 1 25 1 2 13 1 3 16 29 1 7 16 37 MLTSS MHISS 190 3 1 2 89 3 8 10 4 1 2 114 3 3 8 86 3 1 2 81 1 13 16 46 5 8 16 1 3 4 38 1 15 16 49 MLTSS MHISS 320 5...

Page 19: ...PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM 18 D F S S A D F BBS FBS BVS VS...

Page 20: ...PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM 0 1 2 19...

Page 21: ...PHONE ORDER 1 800 633 0032 FAX 1 401 539 2584 WWW VIBCO COM VIBRATORS VIBCO COM 20 MLTSS MLT MHI MHISS...

Page 22: ...SS 3 8 16LN SS 7 16 14LN SS 1 2 13LN SS LOCK NUT STAINLESS STEEL MLTSS 130 MLTSS 190 MLTSS 320 1 1 5 16 18LN SS 3 8 16LN SS 7 16 14LN SS LOCK NUT STAINLESS STEEL 2 1 130SS04 190SS04 302SS04 COVER STA...

Page 23: ...invoice number against which parts were returned must be supplied Orders for equipment built to specifications which vary from VIBCO s standard units are not subject to cancellation Responsibility VIB...

Page 24: ...TURB SVC4...

Reviews: