8
Installation
•
Do not touch the copper pipes to avoid distortion and system leakage, while moving the condenser
manually.
1.1.3. Inspection
After the product arrival, you should check the accessories against the packing list. If any parts are found
missing, or damaged, please report to the local offices of the carrier and Vertiv Co. immediately.
1.2. Installation Notes
The installation notes of the condenser are as follows
1.
To ensure the heat dissipation capacity, install the condenser in the place with sufficient airflow. Do not
install it where the coil of the condenser may be obstructed by dust or snow. Ensure that there is no
steam of waste heat around.
2. The condenser must be installed on the ground of outdoor or other room that should be mounted on a
plain surface. It can be an elevated installation by concrete column or steel I-beam, it is required that the
installed base bearing capacity must be 1.5 to 2 times more than the weight of the condenser.
3. To reduce the impact of noise around the environment, the condenser should be installed away from the
residential areas (≥15 m).
4. Be careful not to damage the waterproof layer of the building, when the condenser is installed on the roof
of the building. Please observe the relevant rules of local premises.
5. Position the condenser higher than the indoor unit to ensure normal oil return.
6. Follow the vertical upward installation direction. For the convenience of installation and maintenance,
please install the No.1 system (as shown in Figure 2-4) on the same side of same row (as shown in Figure
2-5 & 2-6)
7. When the condensers are installed front-and-back side by side, please install the same height condensers
(as shown in Table 1-2) in a place (as shown Figure in 2-7) to avoid return airflow short circuit.
8. If the condenser is installed in the place where children are accessible, a fence must be installed to restrict
the entry around the condenser.