10H92873 - rev. 8 - 01/2019 - pag. 8
6.3. APPENDIX A - 90-NET
6.3.1. PARAMETERS SETTING
6.3.1.1. ENABLE EXTERNAL SYNCHONISATION CONTROL
Once all the connections are done as per Installation Manual, switch on QS1 on the first UPS and perform the
following steps:
In PPVis -> Parameter Input -> "[27] Parallel and Ext Sync Configuration", set the following parameters:
• PNU 51 "Access level CU" set to "Experts - Level 3 (3)";
• PNU 799 "SF - Super service" set to "SF 4 (4)";
• PNU 52 "Function selection CU" set to "H/W Init - URL (2)";
• PNU 579 "Enable External synchronization" set to "Synch with external Freq (1)";
Send all the parameters according to the list above (use the send pushbutton);
Once the parameters are at the "Actual Value" return to normal operation as follows:
• PNU 52 "Function selection CU" set to "Return (0)";
• PNU 799 "SF - Super service" set to "SF 0 (0)";
• PNU 51 "Access level CU" set to "Normal Operation - Level (1)";
Then in PPVis -> Parameter Input -> "[14] P75 Inv Special Performance Class", set the following parameters:
• PNU 51 "Access level CU" set to "Experts - Level 3 (3)";
• PNU 799 "SF - Super service" set to "SF 4 (4)";
• PNU 52 "Function selection CU" set to "H/W Init - URL (2)";
• PNU 75.21 "X_UR2_CRE" set to "0" (will later be used to calculate the offset);
• PNU 75.22 "X_UR3_UV" set to "1024";
• PNU 75.23 "X_UR3_IV" set to "1024";
• PNU 75.25 "X_UR3_CRE" set to "4096";
Send all the parameters according to the list above (use the send pushbutton);
Once the parameters are at the "Actual Value" return to normal operation as follows:
• PNU 52 "Function selection CU" set to "Return (0)";
• PNU 799 "SF - Super service" set to "SF 0 (0)";
• PNU 51 "Access level CU" set to "Normal Operation - Level (1)";
• Once back in normal operation open QS1 and the electronics will shut down;
Follow these steps for ALL the units connected to ESB.
6.3.2. OFFSET COMPENSATION TUNING
The parameter 75.21 has been designed to compensate the phase error, introduced by the UPS control, be-
tween the frequency reference coming from the ESB and the inverter output signal.
To carry out this procedure an oscilloscope between reserve input and inverter output must be used. The ESB
must be already installed and interconnected to the UPS system. The PNU 579 must be already loaded and
set to 1.
The PNU 75.21 calibration must be done on each UPS composing the system.
Please, perform the following steps:
• Connect your oscilloscope to the first UPS;
(Connect "Channel 1" to "Bypass Input L1 & N" and "Channel 2" to "UPS Output L1 & N", as shown in the following
figure)
Summary of Contents for 10H92873
Page 2: ...10H92873 rev 8 01 2019 pag 2...
Page 21: ...10H92873 rev 8 01 2019 pag 17...
Page 26: ...10H92873 rev 8 01 2019 pag 22...
Page 43: ...10H92873 rev 8 01 2019 pag 43...
Page 48: ...10H92873 rev 8 01 2019 pag 48...
Page 65: ...10H92873 rev 8 01 2019 pag 65...
Page 70: ...10H92873 rev 8 01 2019 pag 70...
Page 87: ...10H92873 rev 8 01 2019 pag 87...
Page 92: ...10H92873 rev 8 01 2019 pag 92...
Page 109: ...10H92873 rev 8 01 2019 pag 109...
Page 114: ...10H92873 rev 8 01 2019 pag 114...
Page 131: ...10H92873 rev 8 01 2019 pag 131...
Page 136: ...10H92873 rev 8 01 2019 pag 136...
Page 140: ...10H92873 rev 8 01 2019 pag 140 5 2 Puc 4 90NET B...
Page 141: ...10H92873 rev 8 01 2019 pag 141 5 3 VERTIV UPS Vertiv Puc 5 Puc 5 Vertiv...
Page 153: ...10H92873 rev 8 01 2019 pag 153...
Page 157: ...10H92873 rev 8 01 2019 pag 157 6 7 Puc 19 UPS Vertiv UPS CROSS Puc 19 slave 2 A master...
Page 158: ...10H92873 rev 8 01 2019 pag 158...
Page 175: ...10H92873 rev 8 01 2019 pag 175...
Page 180: ...10H92873 rev 8 01 2019 pag 180...
Page 197: ...10H92873 rev 8 01 2019 pag 197...
Page 202: ...10H92873 rev 8 01 2019 pag 202...