NOTES ON RUNNING 
Before Connecting the power supply and running the Fan Check… 

Are all links and wiring complete as per wiring diagram? 
Are all fixings secured? 
Are all relevant guards fitted? 
Are all Circuit protection devices fitted? 
Are all Terminal box covers and sealing glands secured? 
Are all Earth connections secured? 
Check that no hazard exists for persons in the locality of the fan.  Switch on the fan and 
check that the fan rotation is correct as per the direction arrows on the fan plate/casing. 
If not isolate power supply and check wiring. Check that the current (amps) taken by 
the fan does not exceed the current shown on the rating plate. 

 

 

INSTALLER AND ELECTRICAL CONTRACTOR RESPONSIBILITY 

Vent-Axia Ltd, as suppliers of the equipment cannot be responsible for the final 
installation and electrical connection of the product on site. We have made reasonable 
effort to offer guidance and assistance but the installer and electrical contractor on site 
have a responsibility for ensuring the equipment is safely and securely installed and 
electrically/mechanically safe in accordance with statutory requirements. 
The fans are supplied as a component to be incorporated into a ventilation system. The 
final complete system installation that includes the fans MUST meet the requirements 
of:- 
Low voltage Directive 72/23/CEE 
Machinery Directive 89/392/CE 
Electromagnetic Compatibility Directive 89/336/CE 
If the fan is installed in an area where there is possible danger to safety or health then 
guards MUST be fitted.  
Guards suitable for many applications are available from Vent-Axia Ltd. 
Please remember that fans need maintenance, cleaning and inspection.  Allow for 
reasonable access for these operations to be carried out safely. 
If in doubt, please ask. 
 

 

 

ROUTINE INSPECTION/MAINTENANCE

 

THIS MUST BE UNDERTAKEN BY A COMPETENT PERSON. 
ISOLATE  UNIT  FROM  ELECTRICAL  SUPPLY  AND  ENSURE  THAT  IT  CANNOT  BE 
ACCIDENTALLY TURNED BACK ON. 

1.

 

We recommend that after three months the fan should be inspected and cleaned 

to remove deposits on the impeller or motor. Thereafter, it should be checked and 
cleaned periodically as experience dictates, or at least twice a year.  

2.

 

If a build-up of dirt/deposits is evident then this should be carefully cleaned off.  

Please take care not to damage the fan or affect the balance of the impeller motor 
assembly (balance weights may be fitted to the impeller). 

3.

 

The fan motors are fitted with ‘sealed for life’ bearings and should not require 

maintenance under normal circumstances. 

 
 

Summary of Contents for QPTW Series

Page 1: ...E READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING INSTALLATION THESE INSTRUCTIONS SHOULD BE LEFT WITH THE END USER Acoustic Fans Twin In line Duct Fan Range QPTW QPTW100C QPTW125C QPTW150C QPTW160C QP...

Page 2: ...ake appropriate action to reduce sound levels A range of products are available for this purpose from Vent Axia This appliance is not intended for use by persons including children with reduced physic...

Page 3: ...and attenuators 5 For horizontal installations parallel fixing brackets are provided for both sides of the unit Fig 1 and extra fixing holes are provided for additional hanger rods 6 All twin units h...

Page 4: ...ired an ancillary circuit will be required with the TK switch connected into the circuit See page 6 for instructions 6 Connect the power supply from the local isolator via any appropriate controls if...

Page 5: ...onent to be incorporated into a ventilation system The final complete system installation that includes the fans MUST meet the requirements of Low voltage Directive 72 23 CEE Machinery Directive 89 39...

Page 6: ...roduct Changeover Panel Changeover Panel with duty share eDemand Changeover Panel QPTW100C 10314200 10314210 QPTW125C 10314200 10314210 QPTW150C 10314200 10314210 QPTW160C 10314200 10314210 QPTW200C 1...

Page 7: ...7 Fig 1 QPTW100C QPTW125C QPTW150C QPTW160C QPTW200C QPTW250C QPTW315C Connected to a changeover panel...

Page 8: ...8 Fig 2 QPTW400C QPTW500C Connected to a changeover panel...

Page 9: ...9 Fig 3 QPTW100C QPTW125C QPTW150C QPTW160C QPTW200C QPTW250C QPTW315C Connected to a changeover panel and auto transformer controller...

Page 10: ...10 Fig 4 QPTW400C QPTW500C Connected to a changeover panel and auto transformer controller...

Page 11: ...11 Fig 5 QPTW400C QPTW500C Connected to a changeover panel and auto transformer controller...

Page 12: ...ex RH10 9YX UK NATIONAL CALL CENTRE Newton Road Crawley West Sussex RH10 9JA SALES ENQUIRIES Tel 0844 8560590 Fax 01293 565169 TECHNICAL SUPPORT Tel 0844 8560593 Fax 01293 539209 For details of the wa...

Reviews: