Operations sequence
General instructions
57
cpg
.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 24/06/2016
7.8
cpg.1-f1
cubicle
Figure 7.62
Initial situation for
cpg.1-f1
cubicle
7.8.1 Commissioning the cubicle
Initial conditions
: switch-disconnector open
and earthing switch open.
1. Connect the circuit breaker - disconnector by turning
the lever clockwise.
Figure 7.63
Lever turn detail
2. Check the change of status of the circuit breaker -
disconnector position indicator.
Figure 7.64
Switch - disconnector closed detail
To put the equipment out of commission,
reverse the sequence of operation.