the two
short
screws provided. (See Last Page)
Proper Procedure To Open the TPT1210-1-IW Dock For Mounting
Step 1 (see photo 1)
Place dock on secure counter or table, hold firmly in both
hands and press both side inward until it bottoms out.
Step 2 (see photo 2)
Release grip enough to allow floating dock plate to extend out
of dock
Step3 (see photos 3 and 4)
Lift the floating dock plate up exposing the foam packing
material and remove all packing material
Step 4 (see photo 5)
Carefully open the floating dock, exposing attachment holes
used to connect the dock to the TPT1210-1-INSTALL-16 KIT or
directly to extendable mounting brackets
Step 5 (see photos 6 and 7)
With the dock facedown, identify the high-voltage and
network connection ports on back. Remove the screws holding
the high voltage cover.
Step 6 (see photo 8)
A qualified electrician will make high voltage connections to
the appropriate wires. Replace cover when finished
Step 7 (see photo 9)
Connect the local network cable via a standard RJ-45 Ethernet
connection. If using as an in wall application only, record the
MAC address of the docking station for future reference.
Step 9 (see photo 10)
The TPT1210-1 In-Wall Docking station is now ready to be
mounted. Repeat steps 1 and 4 to expose the mounting holes