CT-6500 Series 2 Operating Instructions
32
9.1.4 Timing OPEN-CLOSE-OPEN Operation
The OPEN-CLOSE-OPEN operation requires the user to enter two time-delays
between the circuit breaker operations. The time delays are in millisecond intervals.
The first delay is from the first OPEN command to the CLOSE command. The second
delay is from the CLOSE command to the second OPEN command. Refer to Table 6.0
for setting up the OPEN-CLOSE-OPEN operation.
Table 6.0 Open-Close-Open Operation Using Delay
STEP
OPERATION
ACTION
DISPLAY
1
READY TIMER FOR BREAKER OPERATION.
PRESS #1 KEY.
INSERTION RESISTOR?
1.NO
2.YES
2
SELECT NO INSERTION RESISTOR.
PRESS #1 KEY.
TIMING WINDOWS:
1.WINDOW = 1 SEC
2.WINDOW = 10 SEC
3.WINDOW = 20 SEC
3
SELECT 1-SECOND WINDOW.
PRESS #1 KEY.
TRIGGER MODE:
1.INTERNAL TRIGGER
2.EXTERNAL TRIGGER
4
SELECT INTERNAL TRIGGER.
PRESS #1 KEY.
TIMING MODE:
1. OPEN
2. CLOSE
3. O-C
4. C-O
5. O-C-O
5
SELECT OPEN-CLOSE-OPEN OPERATION.
PRESS #5 KEY.
O-C Delay in mS:
(10 – 350)
mSec
ENTER when done
6
SELECT DELAY BETWEEN OPEN-CLOSE
OPERATION.
ENTER DELAY USING
0-9 KEYS, PRESS THE
“ENTER” KEY TO
CONFIRM.
C-O Delay in mS:
(10 – 350)
mSec
ENTER when done
7
SELECT DELAY BETWEEN CLOSE-OPEN
OPERATION.
ENTER DELAY USING
0-9 KEYS, PRESS THE
“ENTER” KEY TO
CONFIRM.
OPEN-CLOSE-OPEN TIMING
Hold "ARM" Switch,
Then "START".
"STOP" to ABORT
8
INITIATE O-C-O COMMAND.
HOLD THE "ARM"
SWITCH AND
PRESS THE "START"
KEY.
TEST IN PROGRESS
Hold "ARM" Until
Test complete.
(Up to 25 seconds)
9
ANALYZER IS READY TO OUTPUT RESULTS.
NONE.
1.RUN TEST 06/12/07
2.GET RSLT 19:20:01
3.SET-UP
4.DIAGNOSTIC
Summary of Contents for CT-6500 2 Series
Page 22: ...CT 6500 Series 2 Operating Instructions 21 Figure 4 0 Series Contact Cable Connection...
Page 77: ...CT 6500 Series 2 Operating Instructions 76 APPENDIX F SIEMENS TCP Breaker Velocity Calculation...
Page 79: ...CT 6500 Series 2 Operating Instructions 78 APPENDIX H CT 6500 SIEMENS SPS2 Test Plan...
Page 82: ...www vanguard instruments com...