4.

 

Connect the inlet and outlet tubing to the reservoir fittings and adjust the reservoir liquid level 
by turning the hollow overflow weir screw up or down with the provided Allen wrench, see

 

Figure 5.  If you are not going to be continuously adding solution, adjust the overflow weir to 
the highest level and place the inlet and overflow covers to prevent particulates from collecting 
in these areas as shown in Figures 4. 

 

 

Figure 2. Illustrates the VP 756CP-96B Reservoir and the VP 763B Drive Unit 

with the alignment pins to register the Reservoir into the correct position

 

 
5.

 

Connect the heating/chilling tubing to the base inlet and outlet fittings. 
 

6.

 

Plug the Control Unit into a 100-240 Volts, 50/60 Hz outlet.  Connect the VP 763B Drive Unit to 
the Control Unit with the control cable.   
 

7.

 

Set the Speed Control Knob to 0.  Turn on the power switch.  Slowly increase Knob to 15.   
 

8.

 

Carefully add the sample liquid to the reservoir after the unit is running.  This prevents 
particulates from settling out.  If the reservoir is attached to a peristaltic pump system, have the 
unit running before the pump is turned on.  We recommend running the pump system 
continuously and recycling the overflow back to the source container.  Alternatively, the inlet 
flow rate can be matched to the pipetting rate and the overflow can be used as an emergency 
measure. 

 
 
 