MM101 – D-4E HOT MELT UNIT
94
VALCO MELTON S.L.U. Pol. Ind. Agustinos C/G 34 3116 0 ORCOYEN, NAVARRA
TEL: +34 948 321580 Fax: +34 948 326584 [email protected]
www.valcomelton.com
APPENDIX B - POWER
REQUIREMENTS
Warning!
Calculate all power requirements as stated below before
hooking up power. OTHERWISE, DAMAGE TO
EQUIPMENT AND/OR THE CIRCUIT COULD OCCUR,
POSSIBLY RESULTING IN INJURY AND DEATH TO.
The power requirements of the D4-E System (unit, hoses, and guns) must
be calculated before hooking up power to verify that the hoses and guns do
not exceed the power rating of the D4-E unit. Serious damage to the
equipment and the circuit as well as injury to personnel can occur from
overloading the system.
This calculation will depend on the following three factors:
•
The wattage of any one hose or gun.
•
The wattage of any hose/gun pair.
•
The total wattage of all hoses and guns.
Perform the system power requirement calculation for the 120 VAC unit as
follows.
1. The power requirement of any hose or gun is listed on the
data tag of the component. List the power requirement of
each component and compare these values to the
maximum wattage for any one hose or gun given in Line 1
of Table B-1.
2. Add the power requirements of hose 1 and gun 1. Compare
this value to the maximum wattage for any hose/gun pair
given in Line 2 of Table B-1.
3. Add the power requirements of all hoses and all guns.
Compare this value to the maximum wattage for all hoses
and guns given in Line 3 of Table B-1.
4. If any of the power requirements calculated in steps 1-3
exceed any of the maximum allowable wattages given in
Table B-1, then the hose length or the gun configuration
must be changed to reduce all power requirements to
below maximum allowable wattages.
If each of the power requirements calculated in steps 1-3 is
below the maximum allowable wattages given in Table B-1,
then the power requirement of the system is within
allowable limits
System Power
Requirement
Calculation –
120VAC D4-E
Unit